Third Notice | | 2/12/2020 | 2/18/2020 | | DONE |
|
|
|
This permit finaled on the web by Caloub Huttash
|
Second Notice | | 1/9/2020 | 2/7/2020 | | DONE |
|
|
|
mailed 2-10-20
|
First Notice | | 12/12/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
Permanent Occupancy | | | 12/2/2019 | | DONE |
|
|
|
|
BLD-Final | 11/26/2019 | 11/26/2019 | 11/26/2019 | P | PASS |
Mike Jordan
|
|
|
Please give me a call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. Ok for perm occ.
|
FIRE-Final Inspection | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
Zoning Approval | 11/26/2019 | 11/26/2019 | 11/26/2019 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 11/18/2019 | 11/19/2019 | 11/19/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for the fire sprinkler system and fire extinguishers. Provide interconnect of the door mags and the fire alarm system as per the iFC. This work requires permit.
Call me when you’re headed this way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Ceiling Grid Inspection | 10/23/2019 | 10/24/2019 | 10/24/2019 | A | PASS |
Mike Jordan
|
|
|
Call me when you’re headed this way please. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Mike Jordan
|
|
|
Inspect fat grid from grid line 4 east. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Ceiling Grid Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Mike Jordan
|
|
|
Inspect fat grid from grid line 4 east. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Energy code compliance | 8/27/2019 | 8/27/2019 | 8/27/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Mike Jordan
|
|
|
Please look at exterior walls for cover. Phone #: ###-#### Inspection requested via web by Bob Thornton. Ok to insulate exterior walls.
|
BLD-Wall cover | 8/12/2019 | 8/13/2019 | 8/13/2019 | A | PASS |
Mike Jordan
|
|
|
Look at vestibule walls. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall Bracing | 8/13/2019 | 8/13/2019 | 8/13/2019 | A | PASS |
Mike Jordan
|
|
|
Look at vestibule walls. Phone #: ###-#### Inspection requested via web by Bob Thornton. Parapet wall bracing is now ok.
|
BLD-Wall cover | 8/6/2019 | 8/7/2019 | 8/7/2019 | P | CANC |
Mike Jordan
|
|
|
Parapet wall bracing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Mike Jordan
|
|
|
Parapet wall bracing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall Bracing | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | FAIL |
Mike Jordan
|
|
|
Parapet wall bracing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Wall cover | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | CANC |
Mike Jordan
|
|
|
Look at the roof wall bracing. Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
|
BLD-Framing/Rough-in | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Mike Jordan
|
|
|
Partial framing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton. West side parapet wall ok per RFI from engineer.
|
BLD-Framing/Rough-in | 7/29/2019 | 7/29/2019 | 7/29/2019 | P | PASS |
Mike Jordan
|
|
|
Partial framing. Give me a call. Phone #: ###-#### Inspection requested via web by Bob Thornton. Stell stud framing for exterior canopies and store front.
|
FIRE-Conference | 7/12/2019 | 7/15/2019 | 7/15/2019 | A | DONE |
Troy Cobbley
|
|
|
Bob and I discussed a concealed space that will be built as "non-combustible" therefore not requireing fire sprinkler protection. Please call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | CANC |
Mike Jordan
|
|
|
Bob- please call before arriving Phone #: ###-####
|
BLD-Conference | 7/12/2019 | 7/12/2019 | 7/12/2019 | A | DONE |
Mike Jordan
|
|
|
Bob- please call before arriving Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/11/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/26/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 6/14/2019 | 6/14/2019 | 6/26/2019 | | DONE |
Julie Romig
|
|
|
06/21 - IBC Rev Comp - Plan Mod Lyle Pearson Jaguar - exterior site changes
|
Routing PW Grading-Hillside | 6/17/2019 | | 6/26/2019 | | PASS |
Melissa Jannusch
|
|
|
No work in sloped area.
|
Permit Ready to Issue | | | 6/26/2019 | | DONE |
|
|
|
PLAN MOD
|
Routing - Design Review | 6/17/2019 | | 6/24/2019 | | PASS |
Josh Wilson
|
|
|
Ok per DRH19-00229
|
BLD-Footing | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PART |
Mike Jordan
|
|
|
Bob-footing for building portion only-per Bob plan mod not for this portion Phone #: ###-####. Footings for new store front. WIP. Will be ok for concrete pending special inspection.
|
Routing - PLAN CHECK | 6/17/2019 | | 6/20/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - Erosion and Sediment | 6/17/2019 | | 6/20/2019 | | PASS |
Michael Zawacki
|
|
|
Passed per ePlanReview
|
Routing - PUBLIC WORKS | 6/17/2019 | | 6/20/2019 | | PASS |
Morgan Webb
|
|
|
Passed per ePlanReview
|
Plan Modification Accepted | | | 6/14/2019 | | DONE |
|
|
|
demo existing concrete paid in front of existing building. A new pad and parking area is to be installed. Existing areas have asphalt removed and stamped concrete installed
|
BLD-Footing | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | DEFR |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Concrete placed in the am. Special inspector on site.
|
Fees Due Hold | 6/1/2019 | | 6/6/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
|
OVERRIDE | | | 5/31/2019 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/31/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2019 | | DONE |
|
|
|
Emailed GC and applicant to inform them the engineer's plan mod fee was missed and that there is a fee due.
|
Permit Ready to Issue | | | 5/31/2019 | | DONE |
|
|
|
DO NOT ISSUE PERMT- plan mod
|
Plan assigned to (JAR) | 5/13/2019 | 5/13/2019 | 5/30/2019 | | DONE |
Julie Romig
|
|
|
05/24 - Plan Mod - Lyle Pearson Jaguar - North Exterior Wall
|
Routing - PLAN CHECK | 5/13/2019 | | 5/30/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - Design Review | 5/13/2019 | | 5/28/2019 | | PASS |
Katelyn Menuge
|
|
|
Plan Modification to push north exterior wall out 20" and modify the height of the storefront window system.
|
Routing Off Site - STRUCTURAL | 5/13/2019 | | 5/24/2019 | | PASS |
Julie Romig
|
|
|
AHJ
|
Plan Modification Accepted | | | 5/13/2019 | | DONE |
|
|
|
Push the N wall out an additional 20" from what was originally proposed and modify the height of the proposed storefront window system. Plan mod requested by R. Damon Beard. Sheets to be A1.1, A1.3, A1.5, A1.7, A2.1, A3.0, A4.0, A5.0, A6.0, A6.2, A8.0, A8.1, A9.0, A10.0, E1.0, E2.0, E2.1, E2.2, All structural sheets.
|
Issue PAID IN FULL permit | | | 3/18/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/18/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 3/4/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 11/5/2018 | 11/5/2018 | 3/4/2019 | | DONE |
Julie Romig
|
|
|
03/06 - 1st Rev Comp - 2nd Rev - L3 Landrover/Jaguar TI
|
Routing - PLAN CHECK | 2/28/2019 | | 3/4/2019 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 2/28/2019 | | 3/4/2019 | | PASS |
Julie Romig
|
|
|
AHJ
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/4/2019 | | DONE |
|
|
|
MET
NEED
RP
MET
GC FORM
REVISED VALUE
|
Route to Impact Fee Review | 12/6/2018 | 12/9/2018 | 12/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 11/5/2018 | 11/5/2018 | 12/6/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 12/6/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 11/5/2018 | | 12/5/2018 | | FAIL |
Julie Romig
|
|
|
Report emailed to applicant.
|
Routing Off Site - STRUCTURAL | 11/5/2018 | | 11/19/2018 | | FAIL |
Julie Romig
|
|
|
AHJ
|
Routing - Erosion and Sediment | 11/5/2018 | | 11/13/2018 | | PASS |
Michael Zawacki
|
|
|
Waiver request approved.
|
Routing - MECHANICAL | 11/5/2018 | | 11/7/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 11/5/2018 | | 11/6/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/5/2018 | | 11/6/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLANNING | 11/5/2018 | | 11/5/2018 | | PASS |
David Moser
|
|
|
|
Routing - Design Review | 11/5/2018 | | 11/5/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH17-00380
|
Intake Approval | | | 11/2/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/26/2018 | | FAIL |
Joe Bruce
|
|
|
Please submit the following to complete your prescreen:
1) 1. Fill out and upload form #502 into the documents folder. Since this checklist was missing a complete verification of items could not be completed and additional items might be required.
2) The design review letter of approval DRH17-00566 references the removal of a retaining wall. No exterior changes to the building are permitted from this letter. A letter from planning and zoning will be required for the exterior modifications. Contact Katelyn Menuge ###-#### with any questions regarding this application.
3) Verification of Legal lot or parcel form is missing.
4) Form #310 is missing the owner's signature. Upload form #310 with the required signature.
5) Permanent Operation & Maintenance Agreement form needs to be mailed or dropped off to the public works drainage coordinator. Contact Brian Murphy for more information ###-####.
6) Lighting compliance certificate references out of date code (2012 IECC). Revise the COMcheck lighting compliance certificate on page E0.1 to have the correct energy code (2015).
7) Plan sheets (A1.1, A10.0, A8.1, A9.0, do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp.
8) Building envelope COMcheck analysis for new addition could not be located on the drawings.
|
Application received | | | 10/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2018 3:36PM
|