First Notice | | 12/8/2018 | 11/29/2018 | | DONE |
|
|
|
This permit finaled on the web by Paul Saucerman
|
BLD-Final | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Mike Jordan
|
|
|
Rich Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Rich Phone #: ###-####
|
Permanent Occupancy | | | 11/28/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 11/11/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Jim Sly
|
|
|
Framing inspection - please call Paul 30 minutes before you head over....key is in lockbox on stairway to get into suite - Code 3625 - I can meet you there if time allows...Paul Phone #: ###-#### Inspection requested via web by Paul Saucerman
|
Route to Impact Fee Review | 11/5/2018 | 11/8/2018 | 11/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 11/6/2018 | | DONE |
|
|
|
NEED
REVISED VALUE
MET (paul@saucermanci.com)
GC FORM
|
Issue PAID IN FULL permit | | | 11/6/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/6/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/30/2018 | 10/30/2018 | 11/5/2018 | | PASS |
Javier Guzman
|
|
|
11/05 L1 Perceive Idaho ePlan**
|
Routing - PLAN CHECK | 10/30/2018 | | 11/5/2018 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 11/5/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2018 | | DONE |
|
|
|
|
Routing - Addressing | 10/30/2018 | | 10/31/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/30/2018 | | 10/31/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 10/30/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 10/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 26 2018 9:26AM
|