BLD-Aging Inspection | 8/1/2019 | 8/1/2019 | 8/1/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 7/31/2019 | 7/31/2019 | 7/31/2019 | | DEFR |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | CANC |
Brandon Shaw
|
|
|
|
BLD-Footing | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Dave Hannah
|
|
|
Sergio Phone #: ###-####
|
PubWorks Subgrade Approval | 3/13/2019 | 3/13/2019 | 3/13/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Routing Walk-In (BLD) | 1/30/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 1/30/2019 | | 1/30/2019 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2019 | | DONE |
Michael Hanson
|
|
|
|
Inspection Record Card- Bld | | | 1/30/2019 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 1/30/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/30/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/30/2019 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 1/25/2019 | 1/25/2019 | 1/25/2019 | A | FAIL |
Rob Patrick
|
|
|
Must meet W.U.I.
|
Routing Walk-In (Zoning) | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | FAIL |
Brian McGowan
|
|
|
Construction materials need to meet WUI and need engineering needs to correspond.
|
Routing PW Grading-Hillside | 10/26/2018 | | 10/26/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
1st review completed | | | 10/26/2018 | | FAIL |
Brian McGowan
|
|
|
Construction materials need to meet WUI and need engineering needs to correspond.
|
Routing - PLAN CHECK | 10/26/2018 | | 10/26/2018 | | FAIL |
Brian McGowan
|
|
|
Construction materials need to meet WUI and need engineering needs to correspond.
|
Application received | | 10/26/2018 | | | |
|
|
|
|