Second Notice | | 3/21/2019 | 3/21/2019 | | DONE |
|
|
|
This permit finaled on the web by Dylan Cooper
|
First Notice | 2/21/2019 | 2/21/2019 | 3/11/2019 | | DONE |
Brandon Shaw
|
|
|
mailed 3-12-19
|
BLD-Final | 2/20/2019 | 2/21/2019 | 2/21/2019 | A | PASS |
Brandon Shaw
|
|
|
Jim- please call 30 min ahead Phone #: ###-####
|
DOC - Permit Finaled | 2/21/2019 | 2/21/2019 | 2/21/2019 | P | PASS |
Brandon Shaw
|
|
|
|
Letter of compliance/Occupancy | | | 2/21/2019 | | DONE |
|
|
|
|
BLD-Final | 1/25/2019 | 1/28/2019 | 1/28/2019 | A | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Ok for temp occc. Doors/doorframes and hardware to be installed by mid February.
|
FIRE-Final Inspection | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety will be ok to pass when door hardware is installed and approved. Fire sprinklers and fire alarm are fully functional and all other life safety items are ok. Area can be used if approved by other inspectors.
Jim-please call 30 minutes prior to meet Phone #: ###-####
|
BLD-Framing/Rough-in | 1/2/2019 | 1/3/2019 | 1/3/2019 | A | PASS |
Mike Jordan
|
|
|
Call half hour before to be let in // Jim Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 1/2/2019 | 1/2/2019 | 1/2/2019 | P | NR |
Mike Jordan
|
|
|
call 30 mins ahead- Jim Phone #: ###-####
|
Fees Due Hold | 12/7/2018 | | 12/18/2018 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Bld | | | 12/6/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/6/2018 | | DONE |
|
|
|
|
Telephone call | | | 12/6/2018 | | DONE |
|
|
|
left message for jim about check/payment
|
Route to Impact Fee Review | 11/10/2018 | 11/13/2018 | 11/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 11/5/2018 | 11/5/2018 | 11/13/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 11/08 L1 ClickBank ePlan
|
Routing - PLAN CHECK | 11/13/2018 | | 11/13/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/13/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/13/2018 | | DONE |
|
|
|
MET jimehall13@gmail.com
NEED
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 11/5/2018 | | 11/10/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 11/10/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 11/5/2018 | | 11/6/2018 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 11/2/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 10/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 31 2018 3:19PM
|