Print Statement | | | 5/13/2019 | | DONE |
|
|
|
|
Third Notice | | 4/16/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
Second Notice | | 3/21/2019 | 4/11/2019 | | DONE |
|
|
|
mailed 4-12-19
|
First Notice | | 2/7/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12
|
Permanent Occupancy | | | 1/28/2019 | | DONE |
|
|
|
|
BLD-Final | 1/24/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Jim Sly
|
|
|
Nico-please go as early possible Phone #: ###-####
|
FIRE-Final Inspection | 1/24/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Nico-please go as early possible Phone #: ###-####
|
BLD-Framing/Rough-in | 1/8/2019 | 1/9/2019 | 1/9/2019 | P | PASS |
Jim Sly
|
|
|
Nicol Phone #: ###-####
|
Print Occupancy Form | | | 1/2/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/2/2019 | | DONE |
|
|
|
|
Routing - FIRE | 12/28/2018 | 12/28/2018 | 12/28/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/28/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/28/2018 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 11/15/2018 | | 12/28/2018 | | DONE |
Michael Hanson
|
|
|
12/10 #520 L3 ePlan. 1st review completed - See changemarks and building plan review in ePlan for corrections required. MDH
|
Routing - PLAN CHECK | 12/18/2018 | | 12/18/2018 | | PASS |
Michael Hanson
|
|
|
|
Route to Impact Fee Review | 12/10/2018 | 12/13/2018 | 12/11/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 11/15/2018 | 11/15/2018 | 12/10/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed applicant
|
1st review completed | | | 12/10/2018 | | FAIL |
Michael Hanson
|
|
|
See ePlan documents, building plan review for corrections required. MDH
|
Routing - PLAN CHECK | 11/15/2018 | | 12/10/2018 | | FAIL |
Michael Hanson
|
|
|
See ePlan documents, building plan review for corrections required. MDH
|
Routing - PLANNING | 11/15/2018 | | 11/15/2018 | | PASS |
David Moser
|
|
|
Health club is allowed in C-2 and parking is simlar to retial. Building is part of large shopping center.
|
Routing - Addressing | 11/15/2018 | | 11/15/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/15/2018 | | 11/15/2018 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT
|
Intake Approval | | | 11/13/2018 | | PASS |
|
|
|
|
Intake Approval | | | 11/7/2018 | | FAIL |
Michael Hanson
|
|
|
Provide planning and zoning approval letter for exterior modifications. MDH
|
Application received | | | 11/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 1 2018 10:17AM
|