BLD-Final | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Brandon Shaw
|
|
|
Garage access code is 0820 Phone #: ###-#### Inspection requested via web by Randy Neary
|
DOC - Permit Finaled | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.79
|
BLD-Final | 7/5/2019 | 7/5/2019 | 7/5/2019 | P | NR |
Brandon Shaw
|
|
|
Need to post Blower door test results... Insulate warm/supply side of hot water lines in garage, from water heater to wall...
|
BLD-Wall cover | 4/19/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Randy Neary c/n made ok
|
BLD-Energy code compliance | 4/19/2019 | 4/19/2019 | 4/19/2019 | P | FAIL |
Jim Storey
|
|
|
Thank you. Looking for ok to cover both drywall and siding Have a great day and weekend Phone #: ###-#### Inspection requested via web by Randy Neary
|
BLD-Framing/Rough-in | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Randy Neary nail girder// ok to insulate.
|
BLD-Wall Bracing | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Jim Storey
|
|
|
Shear inspection. Ok to Tavel walls Phone #: ###-#### Inspection requested via web by Randy Neary
|
BLD-Foundation | 3/13/2019 | 3/14/2019 | 3/14/2019 | A | PASS |
Jim Storey
|
|
|
Auggy Phone #: ###-#### wip
|
BLD-Footing | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Set backs per plans...
|
Inspection Record Card- Bld | | | 1/10/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/10/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/8/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 12/6/2018 | 12/6/2018 | 1/8/2019 | | DONE |
Jenny Nelson
|
|
|
12/26 sfd L2 ePlan. 2nd Review 12/14 failed ESC. 1st review complete, need full size plan for sections, failed fire, ESC, and Mechanical.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/8/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 1/8/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/14/2018 | | DONE |
|
|
|
SUEZ documentation of fire flow received.
|
Routing - PLAN CHECK | 12/14/2018 | | 12/14/2018 | | PASS |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 12/11/2018 | | 12/11/2018 | | PASS |
Troy James
|
|
|
Unable to approve in eplan until applicant signs off on their end.
|
Route to Impact Fee Review | 12/6/2018 | 12/9/2018 | 12/7/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 12/6/2018 | 12/6/2018 | 12/7/2018 | | PASS |
Lee G Meredith
|
|
|
Review failed. Applicant to supply letter from SUEZ indicating fire flow availability. Review comments emailed to applicant and Jenny.
12-14-18 Suez fire flow letter received and passed. Fire sprinklers are not required.
|
Routing PW Grading-Hillside | 12/6/2018 | | 12/7/2018 | | CANC |
Melissa Jannusch
|
|
|
No hillisde review required
|
1st review completed | | | 12/7/2018 | | FAIL |
Jenny Nelson
|
|
|
Need full sized plan for sections, failed fire, ESC and mechanical.
|
Routing - PLAN CHECK | 12/6/2018 | | 12/7/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 12/6/2018 | | 12/7/2018 | | FAIL |
Troy James
|
|
|
Emailed corrections to designer.
|
Routing - PLANNING | 12/6/2018 | | 12/6/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 12/6/2018 | | 12/6/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/6/2018 | | 12/6/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 12/6/2018 | | 12/6/2018 | | PASS |
Michael Zawacki
|
|
|
Hillside requirements waived by engineering, no disturbances in hillside zone. Plan waiver request has been ok'd.
|
Plans ACCEPTED BY PLAN TECH | | | 12/6/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/6/2018 | | DONE |
|
|
|
|
Intake Approval | | | 12/6/2018 | | PASS |
|
|
|
|
Intake Approval | | | 12/3/2018 | | FAIL |
|
|
|
Need
flatten layers on A6 Cross Section
|
Intake Approval | | | 11/27/2018 | | FAIL |
|
|
|
Please flatten layers on sheets A1, A3 and A5. Also please leave the bottom right corner open for city approval stamps (see A0, A1, A2 or A4 for example)
|
Meeting | | | 11/26/2018 | | DONE |
|
|
|
Replied to email from Randy to inform him all the documents and plans have been deleted, so he can upload them correctly and in the correct folders.
|
Intake Approval | | | 11/20/2018 | | FAIL |
|
|
|
Please upload all drawing sheets separately and in correct orientation for which they are formatted (landscape vs. portrait), with a minimum size of 24x18 into the drawings folder. Plan/drawing sheets naming must include the first characters of the discipline name (example A1.0_FLOOR PLAN) .(Only documents in the documents folder do not need to be uploaded as individual sheets.)
Please reserve the bottom right corner for the city approval stamp(s).
|
Meeting | | | 11/20/2018 | | DONE |
|
|
|
emailed applicant submittal standards
|
Intake Approval | | | 11/16/2018 | | FAIL |
|
|
|
NEED
full height on elevations (highest point),
plan sheets must be a minimum of 24x18 and uploaded in the landscape format,
plan sheets naming must include the first characters of the discipline name (example A1.0_FLOOR PLAN),
please leave the bottom right corner empty for the city approval stamps
upload your manual J as one file.
|
Application received | | | 11/6/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2018 9:31AM
|