BLD-Final | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | PART |
Jim Storey
|
|
|
for temp co for office area only // Steven Phone #: ###-#### office occ. ok
|
Case Summary (BLD) | | | 12/4/2018 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 12/4/2018 | | DONE |
Javier Guzman
|
|
|
|
Print Occupancy Form | | | 12/4/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/4/2018 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/4/2018 | | |
|
|
|
|
BLD-Final | 11/28/2018 | 11/29/2018 | 11/29/2018 | P | NR |
Jim Storey
|
|
|
Steven Phone #: ###-#### remove storage/ exit system needs revised to what is in warehouse with exit signage noteded to reinsp.
|
FIRE-Final Inspection | 11/28/2018 | 11/29/2018 | 11/29/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications and annual inspection for fire sprinklers is current, no fire alarm modifications, fire exitnguishers are placed but will need to be inspected soon, tires stored in warehouse will need to be removed before C of O, if tires remain then an evaluation of the fire sprinkler system will be required to verify protection is adequate for commodities. Final life fire safety inspection complete.
Steven Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/28/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 11/6/2018 | 11/6/2018 | 11/27/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 11/12 L2 TBCo LLC Occ Eval Paper
|
Routing - PLAN CHECK | 11/27/2018 | | 11/27/2018 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 11/27/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/27/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/27/2018 | | DONE |
|
|
|
met
|
Telephone call | | | 11/27/2018 | | DONE |
|
|
|
Left voicemail for Steven to inform him the permit is ready.
|
Routing - FIRE | 11/20/2018 | 11/20/2018 | 11/20/2018 | | PASS |
Erika Akin
|
|
|
Spoke with applicant. The racking has been removed. No work to be done under this permit. No change of use or occupancy.
Fire extinguishers will be required on each level within a 75 foot travel distance of any location. No combustible storage greater than 12 feet or high hazard storage greater than 6 feet in height without additional review and permit. No comments attached. PDS/ Fire inspector to field verify.
|
1st review completed | | | 11/16/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 11/7/2018 | | 11/16/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | | 11/6/2018 | 11/15/2018 | | FAIL |
Erika Akin
|
|
|
No racking permit for the warehouse space found. Need floor plan, commodity classification, storage heights, aisle widths, ceiling height and packaging details for review.
|
Routing - Addressing | 11/6/2018 | | 11/7/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/6/2018 | | 11/7/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/6/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/6/2018 | | PASS |
Javier Guzman
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/6/2018 | | DONE |
|
|
|
|
Application received | | 11/6/2018 | | | |
|
|
|
|