BLD-Framing/Rough-in | 7/30/2020 | 7/31/2020 | 7/31/2020 | P | PASS |
Jim Storey
|
|
|
Inspection for the last 7 units in building 6 for sheet rock. Gate code is 1379#. There are no fire barrier walls on this inspection. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Framing/Rough-in | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | PASS |
Jim Storey
|
|
|
verify staggered Sheetrock for fire barrier wall. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Framing/Rough-in | 7/16/2020 | 7/17/2020 | 7/17/2020 | P | PASS |
Jim Storey
|
|
|
Partial for cover. Phone #: ###-#### Inspection requested via web by chad stradley
|
PubWorks Occupancy Approval | 5/27/2020 | 5/27/2020 | 5/27/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Framing/Rough-in | 4/14/2020 | 4/15/2020 | 4/15/2020 | P | PASS |
Jim Storey
|
|
|
firewall inspection. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Framing/Rough-in | 3/23/2020 | 3/24/2020 | 3/24/2020 | A | PASS |
Jim Storey
|
|
|
Fire barrier Sheetrock in building 6. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Footing | 3/10/2020 | 3/12/2020 | 3/12/2020 | A | PASS |
Jim Storey
|
|
|
They are set to pour at 2pm on this day. Thank you. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Aging Inspection | 12/30/2019 | 12/30/2019 | 1/2/2020 | | PASS |
Jim Storey
|
|
|
wip
|
Change Expiration Date Only | | | 7/17/2019 | | DONE |
|
|
|
permit reissued by mistake on 7/16/19
|
Print Occupancy Form | | | 7/16/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/15/2019 | | DONE |
|
|
|
DO NOT REISSUE - PLAN MOD
|
Plan assigned to (JHB) | 6/13/2019 | 6/13/2019 | 7/12/2019 | | PASS |
Joe Bruce
|
|
|
(plan mod) Falcon One, Bldg 5
|
Routing Off Site - STRUCTURAL | 7/11/2019 | | 7/12/2019 | | PASS |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 7/11/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 7/8/2019 | | DONE |
Joe Bruce
|
|
|
Emailed comments to architect.
|
Routing - PLAN CHECK | 6/21/2019 | | 7/8/2019 | | PASS |
Joe Bruce
|
|
|
Received reivsed foundaiton plans for restroom.
|
Routing Off Site - STRUCTURAL | 6/21/2019 | | 7/3/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan Modification Accepted | | | 6/13/2019 | | DONE |
|
|
|
Plan mod accepted in e plan-changing footing & framing design -assigned to Joe B
|
Permit Ready to Issue | | | 2/13/2019 | | DONE |
|
|
|
Need
Revised Value- (for each building)
(DO NOT ISSUE WITHOUT ALL PERMITS, BLD18-03877, BLD18-04070 TO BLD18-04076, BLD19-00314 TO BLD19-000317)
|
Issue PAID IN FULL permit | | | 2/13/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/13/2019 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 2/13/2019 | | DONE |
|
|
|
permit reissued by mistake on 7/16/19
|
Plan assigned to (JHB) | 11/14/2018 | 11/14/2018 | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
(3rd Rev Comp) 12/07 - (502) Falcon One Storage Condos Bldg 5
|
Routing Off Site - STRUCTURAL | 2/8/2019 | | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/8/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
Structural resubmittal required.
|
Routing Off Site - STRUCTURAL | 1/30/2019 | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
See structural comment in the Agency Comments folder for remaining issue to address. Provide a complete written response outlining the analysis method you are taking responsibility for.
|
Routing PW Sewer Design | 1/30/2019 | | 1/31/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - FIRE | 1/17/2019 | 1/17/2019 | 1/30/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan resubmittals requested | | | 1/30/2019 | | FAIL |
Joe Bruce
|
|
|
PW Sewer and Structutral have additional comments. **JHB**
|
Plan resubmittals received | | | 1/30/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 1/17/2019 | | 1/28/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 1/17/2019 | | 1/25/2019 | | FAIL |
Joe Bruce
|
|
|
AHJ
|
Routing PW Sewer Design | 1/17/2019 | | 1/23/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Design Review | 1/17/2019 | | 1/18/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Plan Reviewer's activity | | | 1/17/2019 | | DONE |
Joe Bruce
|
|
|
Had applicant upload corrected resubmittal drawings with architect stamp, city approval stamp area, and remove NOT FOR PERMIT language from drawings. **JHB**
|
Plan resubmittals received | | | 1/17/2019 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 12/12/2018 | 12/15/2018 | 12/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 11/14/2018 | 11/14/2018 | 12/12/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing PW Drainage | 12/6/2018 | | 12/12/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 12/6/2018 | | 12/12/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 12/6/2018 | | 12/12/2018 | | FAIL |
DeAnn Brown
|
|
|
Please add tap permit language described in changemarks on sheet C4.0.
|
1st review completed | | | 12/12/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 12/12/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 11/14/2018 | | 12/7/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing - Erosion and Sediment | 11/14/2018 | | 12/6/2018 | | PASS |
Andy J. Long
|
|
|
No ESC review or ESC permit required, ESC permit for project already issued, see ESC18-01289.
|
Routing - PUBLIC WORKS | 11/14/2018 | | 12/6/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing Off Site - STRUCTURAL | 11/14/2018 | | 11/29/2018 | | FAIL |
Joe Bruce
|
|
|
AHJ
|
Routing - MECHANICAL | 11/14/2018 | | 11/26/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 11/14/2018 | | 11/16/2018 | | PASS |
Dan Ediger
|
|
|
Per Plans and ISPC
|
Routing - Design Review | 11/14/2018 | | 11/16/2018 | | FAIL |
Katelyn Menuge
|
|
|
See Changemarks
|
Routing - PLANNING | 11/14/2018 | | 11/15/2018 | | PASS |
Leon Letson
|
|
|
Storage is an allowed use in the M-1D zone.
|
Routing - Addressing | 11/14/2018 | | 11/14/2018 | | PASS |
Doug Chausow
|
|
|
Facility address: 2140 E Summersweet Dr
|
Intake Approval | | | 11/7/2018 | | |
|
|
|
|
Intake Approval | | | 11/7/2018 | | |
|
|
|
|
Intake Approval | | | 11/7/2018 | | PASS |
|
|
|
|
Application received | | 11/7/2018 | | | |
|
|
|
|
Application received | | 11/7/2018 | | | |
|
|
|
|