Second Notice | | 4/13/2020 | 5/5/2020 | | DONE |
|
|
|
This permit finaled on the web by Samantha Tallman
|
Zoning Approval | 4/28/2020 | 4/28/2020 | 4/28/2020 | | PASS |
Katelyn Menuge
|
|
|
|
First Notice | | 3/12/2020 | 4/3/2020 | | DONE |
|
|
|
mailed 4-6-2020
|
Permanent Occupancy | | | 3/2/2020 | | DONE |
|
|
|
|
BLD-Final | 2/27/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Jim Storey
|
|
|
electrical inspection is set for pm Phone #: ###-#### Inspection requested via web by chad stradley final ok pending others
|
FIRE-Final Inspection | 2/27/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguiahers are placed with current inspection tags. Final life fire safety inspection for area of work complete, signature provided on permit sign off card.
electrical inspection is set for pm Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Framing/Rough-in | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PART |
Jim Storey
|
|
|
Fire barrier wall second side to see staggering of Sheetrock Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Framing/Rough-in | 1/23/2020 | 1/24/2020 | 1/24/2020 | P | PART |
Jim Storey
|
|
|
inspect putty pads on outlets Phone #: ###-#### Inspection requested via web by chad stradley 4x4 boxes ok// one pannel needs survace mounted
|
BLD-Framing/Rough-in | 1/23/2020 | 1/23/2020 | 1/23/2020 | P | PART |
Jim Storey
|
|
|
framing and fire wall inspection. Phone #: ###-#### Inspection requested via web by chad stradley 24 inch ele box fire protection <
|
Zoning Approval Temp | 10/18/2019 | 10/18/2019 | 10/18/2019 | | DONE |
Katelyn Menuge
|
|
|
BND19-00190
|
BLD-Footing | 6/4/2019 | 6/6/2019 | 6/6/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by chad stradley
|
CHANGE STATUS TO (ISS) | | | 5/3/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (JHB) | 3/21/2019 | 3/21/2019 | 5/2/2019 | | PASS |
Joe Bruce
|
|
|
05/01 (Plan Mod) Falcon One Storage Condos
|
Routing - PLAN CHECK | 5/1/2019 | | 5/2/2019 | | PASS |
Joe Bruce
|
|
|
**Plan Modificaiton Passed Plan Review**
|
Permit Ready to Issue | | | 5/2/2019 | | DONE |
|
|
|
Plan mod approved (plan mod fees under BLD19-03877 main case)
(DO NOT REISSUE or sign off in eplan with out all three BLD18-04075, BLD18-04076 and BLD19-00317 permits have been changed to issued after plan mod fees are paid)
|
Routing - PLAN CHECK | 4/17/2019 | | 5/1/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 4/17/2019 | | 5/1/2019 | | PASS |
Joe Bruce
|
|
|
AHJ
|
Plan resubmittals requested | | | 5/1/2019 | | DONE |
Joe Bruce
|
|
|
Emailed Matt McAnulty the comments for resubmittal.
|
Plan resubmittals received | | | 5/1/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan Modification Accepted | | | 4/17/2019 | | DONE |
Joe Bruce
|
|
|
PLAN MODIFICATION for buildings #7, #8A, & #8B to revise light gauge metal framing to pre-fab metal building.
|
Plan Modification Accepted | | | 4/16/2019 | | FAIL |
Joe Bruce
|
|
|
5) The metal building drawings do not match the architectural drawings. All architectural drawings must be updated to match the new metal building drawings for buildings 7 and 8. Floorplans, elevations, details, and sections shall be updated to reflect the new structure for buildings 7 and 8. Continuity of fire barrier must be maintained.
|
Intake Approval | | | 3/22/2019 | | FAIL |
Joe Bruce
|
|
|
1) Provide a stamp by an Idaho licensed engineer on the new metal building drawings.
2) The metal building drawings do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block. Verify ALL new plan sheets have the required space for city approval stamp.
3) The metal building drawings to not meet our minimum requirements. Minimum sheet size accepted is 18”x24”.
4) Provide structural calculations for the metal buildings. These shall be stamped/signed by an Idaho licensed engineer.
5) The metal building drawings do not match the architectural drawings. All architectural drawings must be updated to match the new metal building drawings for buildings 7 and 8. Floorplans, elevations, details, and sections shall be updated to reflect the new structure for buildings 7 and 8. Continuity of fire barrier must be maintained.
6) Update sheet G-001 with the new drawings added to the sheet index.
|
Plan Modification Accepted | | | 3/21/2019 | | DONE |
|
|
|
Plan mod accepted in e plan-changes to shructural including footing and framing design for buildings 7 new sheets are S2.7 & S4.7 and struc calcs-assigned to Joe B
|
BLD-Footing | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PART |
Brandon Shaw
|
|
|
BLDG 7, South and West footings... Pend Special Inspection...
|
Permit Ready to Issue | | | 2/13/2019 | | DONE |
|
|
|
Need
Revised Value- (for each building)
(DO NOT ISSUE WITHOUT ALL PERMITS, BLD18-03877, BLD18-04070 TO BLD18-04076, BLD19-00314 TO BLD19-000317)
|
Print Occupancy Form | | | 2/13/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/13/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 11/14/2018 | 11/14/2018 | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
(3rd Rev Comp) 12/07 - (502) Falcon One Storage Condos Bldg 7
|
Routing Off Site - STRUCTURAL | 2/8/2019 | | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/8/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
Structural resubmittal required.
|
Routing Off Site - STRUCTURAL | 1/30/2019 | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
See structural comment in the Agency Comments folder for remaining issue to address. Provide a complete written response outlining the analysis method you are taking responsibility for.
|
Routing PW Sewer Design | 1/30/2019 | | 1/31/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - FIRE | 1/17/2019 | 1/17/2019 | 1/30/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan resubmittals requested | | | 1/30/2019 | | FAIL |
Joe Bruce
|
|
|
PW Sewer and Structutral have additional comments. **JHB**
|
Plan resubmittals received | | | 1/30/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 1/17/2019 | | 1/28/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 1/17/2019 | | 1/25/2019 | | FAIL |
Joe Bruce
|
|
|
AHJ
|
Routing PW Sewer Design | 1/17/2019 | | 1/23/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Design Review | 1/17/2019 | | 1/18/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Plan Reviewer's activity | | | 1/17/2019 | | DONE |
Joe Bruce
|
|
|
Had applicant upload corrected resubmittal drawings with architect stamp, city approval stamp area, and remove NOT FOR PERMIT language from drawings. **JHB**
|
Plan resubmittals received | | | 1/17/2019 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 12/12/2018 | 12/15/2018 | 12/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 11/14/2018 | 11/14/2018 | 12/12/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing PW Drainage | 12/6/2018 | | 12/12/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 12/6/2018 | | 12/12/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 12/6/2018 | | 12/12/2018 | | FAIL |
DeAnn Brown
|
|
|
Please add tap permit language described in changemarks on sheet C4.0.
|
1st review completed | | | 12/12/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 12/12/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 11/14/2018 | | 12/7/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing - Erosion and Sediment | 11/14/2018 | | 12/6/2018 | | PASS |
Andy J. Long
|
|
|
No ESC review or ESC permit required, ESC permit for project already issued, see ESC18-01289.
|
Routing Off Site - STRUCTURAL | 11/14/2018 | | 11/29/2018 | | FAIL |
Joe Bruce
|
|
|
AHJ
|
Routing - MECHANICAL | 11/14/2018 | | 11/26/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 11/14/2018 | | 11/16/2018 | | PASS |
Dan Ediger
|
|
|
Per Plans and ISPC
|
Routing - Design Review | 11/14/2018 | | 11/16/2018 | | FAIL |
Katelyn Menuge
|
|
|
See Changemarks
|
Routing - PLANNING | 11/14/2018 | | 11/15/2018 | | PASS |
Leon Letson
|
|
|
Storage is an allowed use in the M-1D zone.
|
Routing - Addressing | 11/14/2018 | | 11/14/2018 | | PASS |
Doug Chausow
|
|
|
Facility address: 2140 E Summersweet Dr
|
Routing - PUBLIC WORKS | 11/14/2018 | | 11/14/2018 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 11/7/2018 | | |
|
|
|
|
Intake Approval | | | 11/7/2018 | | |
|
|
|
|
Intake Approval | | | 11/7/2018 | | PASS |
|
|
|
|
Application received | | 11/7/2018 | | | |
|
|
|
|
Application received | | 11/7/2018 | | | |
|
|
|
|