Second Notice | | 2/17/2019 | 2/16/2019 | | DONE |
|
|
|
This permit finaled on the web by Justin Dauby
|
First Notice | 1/25/2019 | 1/25/2019 | 2/7/2019 | | DONE |
Mike Jordan
|
|
|
mailed 2-11-19
|
Letter of compliance/Occupancy | | | 2/4/2019 | | DONE |
|
|
|
|
BLD-Final | 1/24/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Mike Jordan
|
|
|
Eric Phone #: ###-####
|
DOC - Permit Finaled | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
FIRE-Final Inspection | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
Eric Phone #: ###-####
|
BLD-Final | 1/9/2019 | 1/9/2019 | 1/10/2019 | P | PART |
Dave Hannah
|
|
|
temp- Eric Phone #: ###-#### ok to use conf rm after fire oks
|
BLD-Framing/Rough-in | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
Inspection Record Card- Bld | | | 11/19/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/19/2018 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 11/14/2018 | 11/14/2018 | 11/16/2018 | | PASS |
Joe Bruce
|
|
|
11/19 L1 Idaho Housing and Finance ePlan
|
Routing - PLAN CHECK | 11/14/2018 | | 11/16/2018 | | PASS |
Joe Bruce
|
|
|
|
1st review completed | | | 11/16/2018 | | DONE |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/16/2018 | | DONE |
Christina Prado
|
|
|
NEED - all met
GC FORM
REVISED VALUE
|
Intake Approval | | | 11/14/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 11/8/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 8 2018 7:58AM
|
Intake Approval | | | 11/8/2018 | | FAIL |
Joe Bruce
|
|
|
1) The sheet index on sheet G0.1 identifies 4 plans sheets in this set. Only 3 sheets have been uploaded into Eplan. Please upload the missing sheets or revised sheet index.
2) Hardware groups and schedule could not be found on sheet A8.1. Provide a hardware schedule to identify the hardware groups on your door schedule.
3) The incorrect mechanical code has been referenced on Sheet G0.1. The current IMC is the 2012 version. Revise code data to correct version.
|