BLD-Aging Inspection | 7/9/2020 | 7/9/2020 | 7/9/2020 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Foundation | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | PASS |
Jim Storey
|
|
|
tar // Kerry Phone #: ###-#### waterprooffing ok for back fill.
|
Plan Reviewer's activity | | | 2/20/2020 | | DONE |
Michael Hanson
|
|
|
Discussed the requirements for structural engineering, stair details, damp-proofing, and emergency escape and rescue openings.
|
BLD-Foundation | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Jim Storey
|
|
|
Robert Phone #: ###-#### rebar ok for house walls
|
Plan Reviewer's activity | | | 1/21/2020 | | DONE |
Michael Hanson
|
|
|
Applicant would like to use a smaller window in the family room. R303.2 exception #1 and #2 are satisified so smaller window is allowed. Not a bedroom / not an egress window.
|
BLD-Footing | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | PASS |
Dave Hannah
|
|
|
robert - Phone #: ###-####
|
Plan Reviewer's activity | | | 11/22/2019 | | DONE |
Michael Hanson
|
|
|
PLM19-04984 has been attached to this permit.
|
BLD-Footing | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Jim Storey
|
|
|
Robert Phone #: ###-####
|
BLD-Other | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | DONE |
Bob Archibald
|
|
|
No work in progress
|
BLD-Conference | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | PASS |
Jim Storey
|
|
|
need plan mod for turning SFD into duplex-please check to make sure no work is being done until they get that plan mod Phone #: ###-#### no work being done.
|
Telephone call | | | 7/16/2019 | | DONE |
|
|
|
call came in that they are changing plans to reflect a duplex instead of a SFD-told customer that there would be impact fees due for the converstion
|
Issue PAID IN FULL permit | | | 1/2/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/2/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 12/5/2018 | | |
|
|
|
|
Plan assigned to (M_H) | 11/8/2018 | | 12/5/2018 | | DONE |
Michael Hanson
|
|
|
11/21 #402 L1 ePlan. 1st review completed - See plan review report for corrections required. MDH
|
Routing - PLAN CHECK | 12/5/2018 | | 12/5/2018 | | PASS |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 12/5/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2018 | | DONE |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 12/5/2018 | | 12/5/2018 | | PASS |
Troy James
|
|
|
Manual j report not required. Installing electric baseboard for heat.
|
Permit Ready to Issue | | | 12/5/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/4/2018 | | DONE |
|
|
|
Resubmittals received 2 sheets of each sheets 1,2,3,4,5-took to Michael Hanson
|
Telephone call | | | 12/3/2018 | | DONE |
Michael Hanson
|
|
|
Called Logan back and discussed the info needed for this permit to move forward. Logan indicated he would meet with his team and try to get the information put together today. MDH
|
1st review completed | | | 11/16/2018 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 11/16/2018 | | 11/16/2018 | | FAIL |
Michael Hanson
|
|
|
See plan review report for corrections required. MDH
|
Routing - MECHANICAL | 11/13/2018 | | 11/16/2018 | | FAIL |
Troy James
|
|
|
Unable to make contact with applicant
|
Routing - PLANNING | 11/9/2018 | | 11/13/2018 | | PASS |
Colleen T Carroll
|
|
|
Must provide 2 compliant paved parking spaces
|
Route to Impact Fee Review | 11/8/2018 | 11/14/2018 | 11/9/2018 | | PASS |
Eric Bilimoria
|
|
|
|
Routing - PUBLIC WORKS | | | 11/9/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/8/2018 | | DONE |
|
|
|
no fees paid at intake
|
Plans ACCEPTED BY PLAN TECH | | | 11/8/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/8/2018 | | PASS |
|
|
|
|
Routing - Addressing | 11/8/2018 | | 11/8/2018 | | PASS |
Doug Chausow
|
|
|
|
Application received | | 11/8/2018 | | | |
|
|
|
|