Second Notice | | 6/20/2019 | 6/25/2019 | | DONE |
|
|
|
This permit finaled on the web by Rhonda Marcum
|
First Notice | 5/22/2019 | 5/22/2019 | 6/10/2019 | | DONE |
Jim Storey
|
|
|
mailed 6-11
|
BLD-Final | 5/21/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Jim Storey
|
|
|
Please call Dan at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum
|
DOC - Permit Finaled | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Please call Dan at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum
|
BLD-Final | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | NR |
Jim Storey
|
|
|
Please call Dan at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum need fire insp.
|
Issue PAID IN FULL permit | | | 5/6/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/6/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/3/2019 | | DONE |
|
|
|
emailed the remaining fees due to- bgraham@ymcins.com, Danny Hamilton & Jill Singer
|
Meeting | | | 4/30/2019 | | DONE |
|
|
|
sent email to david informing permit is going to expire in 7 days.
|
Expiration Notice | 4/15/2019 | 5/6/2019 | 4/15/2019 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (JHB) | 11/15/2018 | 11/15/2018 | 12/6/2018 | | PASS |
Joe Bruce
|
|
|
*(1st Rev Comp)12/03 (L2) - CBRA Room HVAC Improvement (DR, Bldg)
|
Routing - PLAN CHECK | 12/4/2018 | | 12/6/2018 | | PASS |
Joe Bruce
|
|
|
Exterior mechanical exhaust rooftop unit was removed from the scope of this project. **JHB**
|
Routing - MECHANICAL | 12/6/2018 | | 12/6/2018 | | PASS |
Chad Schwendiman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/6/2018 | | DONE |
|
|
|
(need JV account if GC is not paying fee)
MET- Need
GC Form
Revised Cert of Value
|
Routing - Design Review | 12/4/2018 | | 12/5/2018 | | PASS |
KayCee Babb
|
|
|
No Design Review required due to exterior alterations being removed from scope.
|
Plan resubmittals received | | | 12/4/2018 | | DONE |
Joe Bruce
|
|
|
Received resubmittal in ePlan. Applicant has removed the rooftop exhaust fan from the scope. **JHB**
|
Route to Impact Fee Review | 11/29/2018 | 12/2/2018 | 11/30/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 11/15/2018 | | 11/29/2018 | | FAIL |
Joe Bruce
|
|
|
|
1st review completed | | | 11/29/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 11/29/2018 | | DONE |
Joe Bruce
|
|
|
Routed ePlan task back to applicant. **JHB**
|
Routing - MECHANICAL | 11/15/2018 | | 11/23/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - Design Review | 11/15/2018 | | 11/15/2018 | | FAIL |
KayCee Babb
|
|
|
A Zoning Certificate is required for the proposed project due to the equipment exceeding the height of the existing parapet.
|
Intake Approval | | | 11/14/2018 | | PASS |
Joe Bruce
|
|
|
|
Application received | | | 11/8/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 8 2018 9:52AM
|
Intake Approval | | | 11/8/2018 | | FAIL |
Joe Bruce
|
|
|
1) The incorrect mechanical code is listed on sheet G0.1. The currently adopted mechanical code is the 2012 version. Update the cover sheet to the correct code cycle.
|