BLD-Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Tony Young
|
|
|
Inspection requested via web by Scott Asin
|
DOC - Permit Finaled | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | DONE |
Tony Young
|
|
|
Inspection requested via web by Scott Asin// 4.7
|
BLD-Energy code compliance | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PASS |
Tony Young
|
|
|
Inspection requested via web by Scott Asin
|
BLD-Framing/Rough-in | 3/6/2019 | 3/7/2019 | 3/7/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,, ok to insulate,, truss fixes are ok now
|
BLD-Framing/Rough-in | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,, engineered fix not done correct,, needs new engineered fix to fix
|
BLD-Framing/Rough-in | 2/28/2019 | 3/1/2019 | 3/1/2019 | P | PART |
Tony Young
|
|
|
The framer fixed all the blocking and straps that were called out. The truss company is working on a fix for the bearing points. I just want to get an ok to insulate. If I am ok then no need for an inspection until the truss company gets the fix. Thanks Phone #: ###-#### Inspection requested via web by Scott Asin// ok to insulate unaffected areas
|
BLD-Framing/Rough-in | 2/27/2019 | 2/28/2019 | 2/28/2019 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,, truss issues,, do not insulate
|
BLD-Wall Bracing | 1/31/2019 | 2/1/2019 | 2/1/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Wall Bracing | 1/31/2019 | 1/31/2019 | 1/31/2019 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,, need to re-nail some areas
|
BLD-Foundation | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | PASS |
Jim Sly
|
|
|
wall // Victor Phone #: ###-####
|
BLD-Footing | 12/26/2018 | 12/27/2018 | 12/27/2018 | A | PASS |
Tony Young
|
|
|
Armando Phone #: ###-####
|
OVERRIDE | | | 12/18/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 11/16/2018 | 11/16/2018 | 12/18/2018 | | DONE |
Jenny Nelson
|
|
|
11/29 sfd L1 ePlan. 1st review done, failed planning
|
Issue PAID IN FULL permit | | | 12/18/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/18/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 12/18/2018 | | 12/18/2018 | | PASS |
Leon Letson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/18/2018 | | DONE |
|
|
|
met
|
Routing - PLANNING | 11/21/2018 | | 11/21/2018 | | FAIL |
Leon Letson
|
|
|
|
1st review completed | | | 11/21/2018 | | FAIL |
Jenny Nelson
|
|
|
Failed planning
|
Routing - PLAN CHECK | 11/16/2018 | | 11/21/2018 | | PASS |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 11/16/2018 | 11/19/2018 | 11/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 11/16/2018 | | 11/19/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 11/16/2018 | | 11/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/16/2018 | | 11/16/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/16/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/14/2018 | | FAIL |
|
|
|
Uploaded wrong plans(deleted plans, so the correct plans can be uploaded)
|
Intake Approval | | | 11/14/2018 | | FAIL |
|
|
|
need manual J's and engineering calcs
|
Telephone call | | | 11/13/2018 | | DONE |
|
|
|
Left voicemail for Scott to ask him which address is the correct one for this project.
|
Application received | | | 11/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 9 2018 2:08PM
|