BLD-Final | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Dave Hannah
|
|
|
Clint Phone #: ###-####
|
FIRE-Final Inspection | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Jim Page
|
|
|
Demo permit for fire alarm work has been completed, final life fire safety inspection complete.
Clint Phone #: ###-####
|
BLD-Final | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | PART |
Dave Hannah
|
|
|
Call ahead // Clint Phone #: ###-#### ok for temp occ needs to fix ada rest rooms
|
FIRE-Final Inspection | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | PART |
Jim Page
|
|
|
Previously noted items have been corrected. FIR permit has been received for fire alarm demo, TCO is authorized for 30 days for life safety contingent on the work on the FIR permit for the fire alarm is completed, inspected and finaled.
Call ahead // Clint Phone #: ###-####
|
FIRE-Final Inspection | 4/2/2019 | 4/3/2019 | 4/3/2019 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, do not have FIR permit in system for fire alarm work/demo as of this note entry.
call to meet // Tyler Phone #: ###-####
|
FIRE-Conference | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | FAIL |
Jim Page
|
|
|
Fire conference complete. Provide addressing for each suite. Provide sticker on each suite main entry reading "Door to remian unlocked while building is occupied. Fire alarm system that is in place is not code compliant and appears to never have been permitted, fire alarm system needs to be code compliant or verify if fire alarm system can be removed (a permit will be required for fire alarm removal if authorized for demo). Slide bolt locks need to be removed on east exit doors. Provide code compliant locking hardware on suite main entry doors. Provide annual inspection for all fire extinguishers. Gate on east side of building is in the path of egress, gate needs to have code compliant door hardware for egress purposes.
please Tyler for access Phone #: ###-####
|
BLD-Framing/Rough-in | 2/14/2019 | 2/15/2019 | 2/15/2019 | A | PEND |
Tony Young
|
|
|
Tyler Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 1/22/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/22/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/22/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 1/11/2019 | 1/11/2019 | 1/18/2019 | | PASS |
Javier Guzman
|
|
|
Plan Mod Vanilla elan
|
Routing - PLAN CHECK | 1/16/2019 | | 1/18/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 1/16/2019 | | 1/18/2019 | | PASS |
Angela Hardy
|
|
|
Signed off in ePlan by PW General Angela Hardy
|
Permit Ready to Issue | | | 1/18/2019 | | DONE |
|
|
|
Plan mod-please do not re issue
verify if fees have changed
|
Plan Modification Accepted | | | 1/11/2019 | | DONE |
|
|
|
plan mod accepted-modifying the south portion restrooms-sheets A-3.0, A-4.0 & A-5.0-assigned to JG
|
BLD-Conference | 1/9/2019 | 1/10/2019 | 1/10/2019 | P | PASS |
Dave Hannah
|
|
|
Tyler Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/9/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/9/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 11/27/2018 | 11/27/2018 | 12/20/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/10 L2 Vanilla ePlan 12/18
|
Routing - PLAN CHECK | 12/18/2018 | | 12/20/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/20/2018 | | DONE |
|
|
|
NEED- all met (blastproperties@gmail.com)
GC
Rev cert of val
|
Route to Impact Fee Review | 12/11/2018 | 12/14/2018 | 12/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 11/27/2018 | | 12/11/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 12/11/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - Addressing | 11/27/2018 | | 11/28/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/27/2018 | | 11/28/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 11/27/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 11/14/2018 | | FAIL |
Michael Hanson
|
|
|
Provide wall bracing details and information. MDH
|
Application received | | | 11/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 10 2018 11:48AM
|