BLD-Final | 7/1/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Tony Young
|
|
|
Bobby Phone #: ###-####
|
DOC - Permit Finaled | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | PART |
Tony Young
|
|
|
Bobby Phone #: ###-####,, needs post
|
BLD-Energy code compliance | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | DONE |
Tony Young
|
|
|
David Phone #: ###-####,, work in progress
|
BLD-Framing/Rough-in | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Tony Young
|
|
|
David Phone #: ###-####
|
BLD-Other | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | PASS |
Mike Jordan
|
|
|
fire rated soffet // Bobby Phone #: ###-####
|
BLD-Energy code compliance | 4/12/2019 | 4/15/2019 | 4/15/2019 | A | FAIL |
Tony Young
|
|
|
Dave; Phone #: ###-####,, correction notice posted,, prior corrections not complete,, justify insulation issues
|
BLD-Framing/Rough-in | 4/10/2019 | 4/11/2019 | 4/12/2019 | P | NR |
Tony Young
|
|
|
frame re-inspect
|
BLD-Framing/Rough-in | 4/12/2019 | 4/12/2019 | 4/12/2019 | A | PART |
Tony Young
|
|
|
frame re-inspect,, needs truss bracing per engineering,, ok to insulate
|
BLD-Framing/Rough-in | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | PART |
Tony Young
|
|
|
Bobbie Phone #: ###-####,, needs truss gable fix,,(backwards),, truss bracing,, seal holes,, ok to insulate
|
BLD-Wall Bracing | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Marmillion
|
BLD-Wall Bracing | 2/20/2019 | 2/21/2019 | 2/20/2019 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by David Marmillion Inspection cancelled from web by: David Marmillion
|
BLD-Wall Bracing | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Marmillion
|
BLD-Footing | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | PART |
Tony Young
|
|
|
Derik Phone #: ###-####,, work in progress,, grade not shot in,, clean out debris and loose soils
|
Inspection Record Card- Bld | | | 1/23/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/23/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 12/4/2018 | 12/4/2018 | 1/7/2019 | | DONE |
Brian McGowan
|
|
|
12/07 - Corrections Required (2) - Re-assigned from Rob to Brian due to Rob's absence.
|
Routing - PLAN CHECK | 1/7/2019 | | 1/7/2019 | | PASS |
Brian McGowan
|
|
|
As per original review by Rob. Corrections required reviewed by Brian
|
Permit Ready to Issue | | | 1/7/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 12/20/2018 | | 12/20/2018 | | FAIL |
Brian McGowan
|
|
|
Rated wall details required.
|
Plan assigned to (RDP) | 11/28/2018 | 11/28/2018 | 12/4/2018 | | DEFR |
Rob Patrick
|
|
|
Braced Wall Table needs corrected. Re-assigned from Rob to Brian due to Rob's absence.
|
Routing - PLANNING | 11/26/2018 | | 11/29/2018 | | PASS |
Leon Letson
|
|
|
|
1st review completed | | | 11/29/2018 | | FAIL |
Rob Patrick
|
|
|
|
Plan assigned to (BJM) | 11/26/2018 | 11/26/2018 | 11/28/2018 | | DEFR |
Brian McGowan
|
|
|
12/7 sfd L1 ePlan
|
Routing - PLAN CHECK | 11/28/2018 | | 11/28/2018 | | FAIL |
Rob Patrick
|
|
|
Braced Wall table needs corrected.
|
Route to Impact Fee Review | 11/26/2018 | 11/29/2018 | 11/27/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 11/26/2018 | | 11/27/2018 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/26/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/26/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/26/2018 | | PASS |
|
|
|
|
Routing - Addressing | 11/26/2018 | | 11/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/26/2018 | | 11/26/2018 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 11/23/2018 | | FAIL |
|
|
|
Need to reduce file size. Emiled David Marmillion and Mark Wagner
|
Intake Approval | | | 11/21/2018 | | FAIL |
|
|
|
still have not corrected issues-i called David and he will submit the revsions after the designer fixes the sheets
|
Intake Approval | | | 11/13/2018 | | FAIL |
|
|
|
can not read plans and on site plan the building shows it is covering over the property lines.
|
Meeting | | | 11/13/2018 | | DONE |
|
|
|
Emailed Applicant to inform them that alot of the plans can not be read and to reupload them and then resubmitt.
|
Meeting | | | 11/13/2018 | | DONE |
|
|
|
Per david, delete all plans to upload fresh
|
Application received | | | 11/11/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 11 2018 1:52PM
|