BLD-Final | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | DONE |
Tony Young
|
|
|
4.0
|
BLD-Final | 4/25/2019 | 4/29/2019 | 4/29/2019 | P | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin/// correction posted,, BDTest,, frost protection,, fire caulking
|
BLD-Energy code compliance | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | PASS |
Tony Young
|
|
|
Inspection requested via web by Scott Asin
|
BLD-Framing/Rough-in | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
Tony Young
|
|
|
Inspection requested via web by Scott Asin// frame corrections are complete
|
BLD-Energy code compliance | 2/23/2019 | 2/25/2019 | 2/25/2019 | A | NR |
Tony Young
|
|
|
Inspection requested via web by Scott Asin,, need to fix a few areas
|
BLD-Framing/Rough-in | 2/21/2019 | 2/22/2019 | 2/23/2019 | P | PART |
Tony Young
|
|
|
Inspection requested via web by Scott Asin,, ok to insulate
|
BLD-Framing/Rough-in | 2/21/2019 | 2/22/2019 | 2/22/2019 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,, truss fixes,, fire blocking,, ok to i nsulate
|
BLD-Framing/Rough-in | 2/20/2019 | 2/21/2019 | 2/21/2019 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,, needs trades,, truss engineering
|
BLD-Wall Bracing | 2/1/2019 | 2/5/2019 | 2/5/2019 | A | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Wall Bracing | 1/31/2019 | 2/4/2019 | 2/4/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,,
|
BLD-Wall Bracing | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin,, later am
|
BLD-Wall Bracing | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Wall Bracing | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | PART |
Tony Young
|
|
|
Armando Phone #: ###-####
|
BLD-Footing | 1/7/2019 | 1/7/2019 | 1/7/2019 | P | PASS |
Tony Young
|
|
|
Armando Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/21/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/21/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 12/19/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 12/5/2018 | 12/5/2018 | 12/19/2018 | | DONE |
Brian McGowan
|
|
|
11/20 - Corrections Required - Deferred back to Brian
|
Routing - PLAN CHECK | 12/19/2018 | | 12/19/2018 | | PASS |
Brian McGowan
|
|
|
As per RDP original review. (I added the fire rating requirements for side setback and overhang requirements.)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/19/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 12/18/2018 | | 12/18/2018 | | FAIL |
Brian McGowan
|
|
|
Sent back at applicant's request to upload corrected documents in versioning stlye. I was asked to delete the non versioning files in order to get the correct documents.
|
Plan Reviewer's activity | | | 12/18/2018 | | |
Brian McGowan
|
|
|
Sent back at applicant's request to upload corrected documents in versioning stlye. I was asked to delete the non versioning files in order to get the correct documents.
|
Plan assigned to (RDP) | 11/20/2018 | 11/20/2018 | 12/5/2018 | | DEFR |
Rob Patrick
|
|
|
11/20 Failed...Corrections required..Applicant needs to resubmit correctly. Deferred back to Brian.
|
Plan Reviewer's activity | | | 12/4/2018 | | |
|
|
|
12/4 Phoned Scott and left a message with the concerns I have about the dwgs and asked him to call me by tomorrow.
|
Routing - PLAN CHECK | 12/4/2018 | | 12/4/2018 | | FAIL |
Rob Patrick
|
|
|
Talked with Scott and he will get comments to designer.
|
Plan Reviewer's activity | | | 12/4/2018 | | |
|
|
|
Scott called and I talked him through what we need and how the process works. He seemed good to go.
|
Telephone call | | | 11/30/2018 | | |
|
|
|
|
Routing - PLAN CHECK | 11/29/2018 | | 11/29/2018 | | FAIL |
Rob Patrick
|
|
|
Changemarks were not addressed and files were re-named so they didn't version.
|
Routing - PLANNING | 11/27/2018 | | 11/27/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Plan assigned to (BJM) | 11/14/2018 | 11/14/2018 | 11/20/2018 | | DEFR |
Brian McGowan
|
|
|
11/27 sfd L1 ePlan
|
Routing - PLAN CHECK | 11/20/2018 | | 11/20/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
1st review completed | | | 11/20/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections required
|
Routing - MECHANICAL | 11/14/2018 | | 11/16/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 11/14/2018 | 11/17/2018 | 11/15/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 11/14/2018 | | 11/15/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLANNING | 11/14/2018 | | 11/14/2018 | | FAIL |
Colleen T Carroll
|
|
|
Need to show paved driveway to detached garage
|
Routing - Addressing | 11/14/2018 | | 11/14/2018 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 11/14/2018 | | FAIL |
|
|
|
Needs to upload files and documents.
|
Plans ACCEPTED BY PLAN TECH | | | 11/14/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/14/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/14/2018 | | PASS |
|
|
|
|
Meeting | | | 11/13/2018 | | DONE |
|
|
|
Emailed Scott about address and only one drawing was uploaded.
|
Application received | | | 11/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 12 2018 11:07AM
|