BLD-Final | 11/21/2018 | 11/26/2018 | 11/26/2018 | P | PASS |
Brandon Shaw
|
|
|
John Phone #: ###-####
|
DOC - Permit Finaled | 11/26/2018 | 11/26/2018 | 11/26/2018 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 11/23/2018 | 11/26/2018 | 11/26/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passedj
ohn Phone #: ###-####
|
Print Occupancy Form | | | 11/26/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 11/26/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/21/2018 | 11/23/2018 | 11/23/2018 | A | FAIL |
Jim Page
|
|
|
Slide boolt lock on east exterior exit door needs to be removed. Door hardware on same door is in-operable, door hardware will need to be serviced. Install sticker on the main entry with the corrected verbage, "Door to remain unlocked while building is occupied'. Install outlet covers that are missing.
John Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/20/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 11/13/2018 | 11/13/2018 | 11/19/2018 | | DONE |
Julie Romig
|
|
|
11/19 - 528 Tobacco Connection
|
Routing - PLAN CHECK | 11/13/2018 | | 11/19/2018 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 11/19/2018 | | DONE |
Julie Romig
|
|
|
|
Case Summary (BLD) | | | 11/19/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2018 | | DONE |
|
|
|
|
Telephone call | | | 11/19/2018 | | DONE |
|
|
|
Called Steven to advise permit is ready to issue
|
Permit Ready to Issue | | | 11/19/2018 | | DONE |
|
|
|
All met
|
Print Occupancy Form | | | 11/19/2018 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/13/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/13/2018 | | PASS |
Julie Romig
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/13/2018 | | DONE |
|
|
|
|
First Notice | | 12/6/2018 | | | |
|
|
|
|
First Notice | 11/26/2018 | 11/26/2018 | | | |
Brandon Shaw
|
|
|
|
Application received | | 11/13/2018 | | | |
|
|
|
|