BLD-Final | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Dave Hannah
|
|
|
call 30 minutes before // Gordon Phone #: ###-####
|
DOC - Permit Finaled | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Dave Hannah
|
|
|
|
Permit Ready to Issue | | | 11/16/2018 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Telephone call | | | 11/16/2018 | | DONE |
Christina Prado
|
|
|
Called Cory to advise permit is ready and gave fees due
|
Issue PAID IN FULL permit | | | 11/16/2018 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 11/14/2018 | 11/14/2018 | 11/15/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 11/14/2018 | | 11/15/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing PW Flood Plain | 11/14/2018 | | 11/15/2018 | | PASS |
Jason C. Taylor
|
|
|
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance (B.C.C. 11-08). No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
|
1st review completed | | | 11/15/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/15/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/15/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2018 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Routing Walk-In (BLD) | 11/14/2018 | 11/14/2018 | 11/14/2018 | P | PASS |
Josh Bogle
|
|
|
took in for floodplain review
|
Application received | | 11/14/2018 | | | |
|
|
|
|