Fees Due Hold | 7/12/2019 | | 11/7/2019 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Wall Bracing | 9/19/2019 | 9/20/2019 | 9/20/2019 | A | PASS |
Jim Storey
|
|
|
gary- inspection Building 80 Phone #: ###-####need trade permits grouped
|
Issue & PRINT to be Invoiced | | | 7/11/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/11/2019 | | DONE |
|
|
|
|
Extend Review Timeline | | | 5/24/2019 | | DONE |
|
|
|
1st approved 180 day extension per Adele. see documents
|
Permit Ready to Issue | | | 5/23/2019 | | DONE |
|
|
|
Met
Need GC Form
(Revised Value if Micron isnt the GC)
|
Plan assigned to (JHB) | 12/3/2018 | 12/3/2018 | 5/22/2019 | | PASS |
Joe Bruce
|
|
|
05/22 (3rd Rev) 12/06 (L1) - Micron Restroom Remodel, plumbing
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/22/2019 | | DONE |
|
|
|
|
Routing - PLUMBING | 5/17/2019 | | 5/21/2019 | | PASS |
Dan Ediger
|
|
|
per plans and ISPC
|
Plan resubmittals received | | | 5/17/2019 | | DONE |
Joe Bruce
|
|
|
Received resubmittal in ePlan.
|
Routing - PLUMBING | 5/9/2019 | | 5/10/2019 | | FAIL |
Daryl Spivey
|
|
|
|
Routing - PLAN CHECK | 5/7/2019 | | 5/9/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing - PUBLIC WORKS | 5/7/2019 | | 5/8/2019 | | PASS |
Morgan Webb
|
|
|
|
Plan resubmittals received | | | 5/7/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan Reviewer's activity | | | 4/16/2019 | | DONE |
Joe Bruce
|
|
|
Let applicant know that architect license AR-1655 has expired as of Feb. 26, 2019. Proof of license is needed for resubmittal.
|
Route to Impact Fee Review | 12/5/2018 | 12/8/2018 | 12/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 12/5/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 12/5/2018 | | DONE |
Joe Bruce
|
|
|
Sent ePlan task to applicant for resubmittal. **JHB**
|
Routing - PLAN CHECK | 12/3/2018 | | 12/5/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing - PLUMBING | 12/3/2018 | | 12/4/2018 | | PASS |
Daryl Spivey
|
|
|
See redline notes. Install per ISPC.
|
Routing - PUBLIC WORKS | 12/3/2018 | | 12/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 12/3/2018 | | 12/3/2018 | | PASS |
Troy James
|
|
|
No HVAC work shown
|
Intake Approval | | | 11/29/2018 | | PASS |
Joe Bruce
|
|
|
|
Plan Reviewer's activity | | | 11/28/2018 | | DONE |
Joe Bruce
|
|
|
Received email from Troy James stating that a mechanical engineer stamp is not required for the scope of work on plumbing. **JHB**
|
Application received | | | 11/15/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 15 2018 10:22AM
|
Intake Approval | | | 11/15/2018 | | FAIL |
Joe Bruce
|
|
|
Please provide the following to complete your prescreen:
1) All sheets must be stamped and signed by the design professional. Sheet EP3.1, E2.1, and MP2.1 are missing a stamp. Revise and upload drawings.
|