Letter of compliance/Occupancy | | | 10/10/2019 | | DONE |
|
|
|
|
BLD-Final | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | PASS |
Brandon Shaw
|
|
|
Bill Phone #: ###-####
|
DOC - Permit Finaled | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.58
|
BLD-Energy code compliance | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Framing/Rough-in | 4/23/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Wall Bracing | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 12/31/2018 | 1/2/2019 | 1/2/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required
|
BLD-Footing | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
OVERRIDE | | | 12/20/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 11/19/2018 | 11/19/2018 | 12/20/2018 | | DONE |
Brian McGowan
|
|
|
12/06 sfd L2 ePlan - Corrections required.
|
Issue PAID IN FULL permit | | | 12/20/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/20/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/20/2018 | | 12/20/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/20/2018 | | DONE |
|
|
|
emailed walt@wrgann.com
|
1st review completed | | | 12/4/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/19/2018 | | 12/4/2018 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 11/19/2018 | 11/22/2018 | 11/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Flood Plain | 11/19/2018 | | 11/21/2018 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR on File. No floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Plans ACCEPTED BY PLAN TECH | | | 11/19/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/19/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/19/2018 | | PASS |
|
|
|
|
Routing - MECHANICAL | 11/19/2018 | | 11/19/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 11/19/2018 | | 11/19/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 11/19/2018 | | 11/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/19/2018 | | 11/19/2018 | | PASS |
Angela Hardy
|
|
|
|
Application received | | | 11/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 16 2018 11:50AM
|