Letter of compliance/Occupancy | | | 7/26/2019 | | DONE |
|
|
|
|
BLD-Final | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Brandon Shaw
|
|
|
Bill Phone #: ###-####
|
DOC - Permit Finaled | 7/25/2019 | 7/25/2019 | 7/25/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | PASS |
Brandon Shaw
|
|
|
Bill Phone #: ###-####
|
BLD-Energy code compliance | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | CANC |
Brandon Shaw
|
|
|
Bill Phone #: ###-####-as per Bill cancel not ready
|
BLD-Other | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Framing/Rough-in | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Ceiling Grid Inspection | 4/1/2019 | 4/2/2019 | 4/2/2019 | A | PASS |
Brandon Shaw
|
|
|
sheet rock on soffits // Bill Phone #: ###-####
|
BLD-Wall Bracing | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Dave Hannah
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
Issue PAID IN FULL permit | | | 12/7/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/7/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 12/3/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 11/19/2018 | 11/19/2018 | 12/3/2018 | | DONE |
Brian McGowan
|
|
|
12/6 sfd L2 ePlan
|
Plan Reviewer's activity | | | 12/3/2018 | | DONE |
Brian McGowan
|
|
|
Reassigned back to those needing to review Floodpalin
|
Routing PW Flood Plain | 12/3/2018 | | 12/3/2018 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR on File. No floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - PLANNING | 12/3/2018 | | 12/3/2018 | | PASS |
Sue Cummings
|
|
|
Has LOMAR
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/3/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/3/2018 | | DONE |
|
|
|
|
1st review completed | | | 11/29/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/19/2018 | | 11/29/2018 | | PASS |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 11/19/2018 | 11/22/2018 | 11/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Flood Plain | 11/19/2018 | | 11/21/2018 | | FAIL |
Jason C. Taylor
|
|
|
A portion of the subject property is within the regulatory floodplain. This project must comply with the Boise Floodplain Ordinance and submit a floodplain application prior to approval/review of the building permit (B.C.C. 11-08). If you have any questions, please call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 11/19/2018 | | 11/20/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 11/19/2018 | | 11/19/2018 | | FAIL |
Sue Cummings
|
|
|
In flood plain. Needs a floodplain application prior to BLD. permitt per JCT
|
Routing - Addressing | 11/19/2018 | | 11/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/19/2018 | | 11/19/2018 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/19/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/19/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/19/2018 | | PASS |
|
|
|
|
Application received | | | 11/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 16 2018 12:49PM
|