Print Statement | | | 5/30/2019 | | DONE |
|
|
|
|
First Notice | | 4/18/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
BLD-Final | 4/5/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Mike Jordan
|
|
|
Will Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 4/8/2019 | | DONE |
|
|
|
|
BLD-Final | 4/2/2019 | 4/3/2019 | 4/3/2019 | A | PART |
Mike Jordan
|
|
|
Will Phone #: ###-####. ok for temp occ. to stock the store only. Main enterance/exit doors are on back order.
|
FIRE-Final Inspection | 4/3/2019 | 4/3/2019 | 4/3/2019 | A | PASS |
Mike Jordan
|
|
|
Issues have been resolved.
|
Temporary Occupancy | 4/3/2019 | 7/2/2019 | 4/3/2019 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | FAIL |
Mike Jordan
|
|
|
Will Phone #: ###-####. Provide code compliant exit sign over main entry.
|
Print Occupancy Form | | | 3/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/20/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/20/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/20/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 3/1/2019 | 3/4/2019 | 3/4/2019 | P | PASS |
Mike Jordan
|
|
|
Will Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 2/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/22/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/21/2019 | | DONE |
|
|
|
PLAN MOD
|
Plan assigned to (JHB) | 2/19/2019 | 2/19/2019 | 2/20/2019 | | PASS |
Joe Bruce
|
|
|
02/25 (Plan Mod) Fossil BTS #1168
|
Routing - PLAN CHECK | 2/19/2019 | | 2/20/2019 | | PASS |
Joe Bruce
|
|
|
|
BLD-Framing/Rough-in | 2/15/2019 | 2/15/2019 | 2/15/2019 | P | PASS |
Jim Sly
|
|
|
Will Phone #: ###-####
|
BLD-Framing/Rough-in | 2/14/2019 | 2/14/2019 | 2/14/2019 | P | NR |
Mike Jordan
|
|
|
Will Phone #: ###-####. No approved city plans on site. Needs electrical rough in inspection.
|
Plan Modification Accepted | | | 1/28/2019 | | DONE |
Brittany Hill
|
|
|
modification to fixture plan, eplan work flow started
|
Issue PAID IN FULL permit | | | 1/14/2019 | | DONE |
|
|
|
emailed tracyg@horizonretail.com & Nicholass to sign bldg permit
|
Plan assigned to (JHB) | 12/12/2018 | 12/12/2018 | 1/2/2019 | | PASS |
Joe Bruce
|
|
|
*(1st Rev Comp) 12/20 - (L2) Fossil BTS #1168 ePlan
|
Routing - PLAN CHECK | 12/28/2018 | | 1/2/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/2/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/2/2019 | | DONE |
|
|
|
MET tnegrete@core-eng.com
NEED
GC FORM
REVISED VALUE
|
Plan resubmittals received | | | 12/28/2018 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 12/20/2018 | 12/23/2018 | 12/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 12/20/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 12/20/2018 | | DONE |
Joe Bruce
|
|
|
Sent ePlan task back to applicant. **JHB**
|
Routing - PLAN CHECK | 12/12/2018 | | 12/20/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing - Addressing | 12/12/2018 | | 12/19/2018 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/12/2018 | | 12/12/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 12/12/2018 | | 12/12/2018 | | PASS |
Katelyn Menuge
|
|
|
CZC18-00304
|
Routing - MECHANICAL | 12/12/2018 | | 12/12/2018 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 12/11/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 12/5/2018 | | FAIL |
Joe Bruce
|
|
|
1. The Certificate of Value for Mechanical, Plumbing, Electrical, Fire Sprinkler, and Fire Alarm are blank. Please provide the revised values on form #306 stating an estimated value for these trades. Upload this document into the documents folder. .
2. Sheet M1.1 "Plan Note - 8" specifies a new outdoor condensing unit on the roof. Since this is a new unit we require the applicant to submit for a certificate of zoning compliance for new rooftop mechanical equipment. Please contact Katelyn Menuge at ###-####, kmenuge@cityofboise.org
3. If a new rooftop unit is being proposed: provide engineering and structural calculations for the additional roof load of the equipment.
|
Intake Approval | | | 11/23/2018 | | FAIL |
Joe Bruce
|
|
|
|
Application received | | | 11/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 19 2018 10:16AM
|