BLD-Blower Door Test Results | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | DONE |
Tony Young
|
|
|
3,92
|
BLD-Final | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 6/10/2019 | 6/11/2019 | 6/11/2019 | P | NR |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, locked up,, also needs drainage away from home
|
BLD-Conference | 5/30/2019 | 5/30/2019 | 5/31/2019 | P | PEND |
Tony Young
|
|
|
Can you meet me briefly between 1 and 3 PM? Phone #: ###-#### Inspection requested via web by Daniel Appel,, projections in exterior firewall,, needs to get a fix prior to final
|
BLD-Energy code compliance | 4/10/2019 | 4/12/2019 | 4/15/2019 | P | PART |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, work in progress,, ok per Dan
|
BLD-Framing/Rough-in | 4/10/2019 | 4/12/2019 | 4/12/2019 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall cover | 4/10/2019 | 4/12/2019 | 4/12/2019 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | PART |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, ok to insulate,, needs fireblocking,, can be done with insulation
|
BLD-Wall Bracing | 3/26/2019 | 3/26/2019 | 3/27/2019 | P | PASS |
Tony Young
|
|
|
Rest of shear Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall Bracing | 3/22/2019 | 3/22/2019 | 3/22/2019 | P | PASS |
Tony Young
|
|
|
Gyp board shear Phone #: ###-#### Inspection requested via web by Daniel Appel,, exterior layer of drywall ok ,, north side
|
BLD-Conference | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PART |
Tony Young
|
|
|
Fire wall inspection Please call Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, 1st layer of house wall,,, already stood,, could not verify all of the nail pattern
|
BLD-Foundation | 3/12/2019 | 3/13/2019 | 3/13/2019 | A | DONE |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, garage,, work in progress
|
BLD-Footing | 3/6/2019 | 3/6/2019 | 3/7/2019 | P | NR |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Foundation | 2/18/2019 | 2/19/2019 | 2/19/2019 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, basement wall,, almost done,, ok
|
BLD-Foundation | 2/14/2019 | 2/15/2019 | 2/18/2019 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, rebar,, work in progress
|
BLD-Foundation | 2/14/2019 | 2/14/2019 | 2/15/2019 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, basement wall rebar,, work in progress
|
BLD-Footing | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, work in progress on basement footings
|
BLD-Footing | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | NR |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 1/7/2019 | 1/7/2019 | 1/8/2019 | P | PASS |
Jim Sly
|
|
|
3 pm or later please Phone #: ###-#### Inspection requested via web by Daniel Appel Minor corrections
|
Routing - PLANNING | 12/12/2018 | | 12/12/2018 | | PASS |
KayCee Babb
|
|
|
|
Inspection Record Card- Bld | | | 12/12/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/12/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 12/11/2018 | | |
|
|
|
|
Routing - PLAN CHECK | 12/11/2018 | | 12/11/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/11/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 11/20/2018 | | 12/11/2018 | | DONE |
Michael Hanson
|
|
|
12/03 #402 L1 ePlan. 1st review completed - See changemarks in ePlan for corrections required. MDH
|
Routing - Design Review | 12/10/2018 | | 12/10/2018 | | PASS |
KayCee Babb
|
|
|
Per DRH18-00231. Shrubs shall be planted along alley prior to inspection.
|
1st review completed | | | 11/29/2018 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required. MDH
|
Routing - PLAN CHECK | 11/20/2018 | | 11/29/2018 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required. MDH
|
Routing - PLANNING | 11/20/2018 | | 11/26/2018 | | FAIL |
KayCee Babb
|
|
|
XREF DRH18-00231
|
Routing - Design Review | 11/26/2018 | | 11/26/2018 | | FAIL |
KayCee Babb
|
|
|
Plans differ from approval and not all Conditions of Approval met. XREF DRH18-00231.
|
Route to Impact Fee Review | 11/20/2018 | 11/23/2018 | 11/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 11/20/2018 | | 11/21/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/20/2018 | | 11/20/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 11/20/2018 | | 11/20/2018 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/20/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/20/2018 | | PASS |
Candy A. Nichols
|
|
|
|
Application received | | | 11/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 19 2018 11:50AM
|