BLD-Final | 1/30/2020 | 1/31/2020 | 1/31/2020 | A | PASS |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
DOC - Permit Finaled | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Dave Hannah
|
|
|
|
Letter of compliance/Occupancy | | | 1/31/2020 | | DONE |
|
|
|
|
Zoning Approval | 12/18/2019 | 12/18/2019 | 12/18/2019 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Aging Inspection | 11/20/2019 | 11/20/2019 | 11/22/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 11/19/2019 | 11/19/2019 | 11/20/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 7/5/2019 | 7/8/2019 | 7/8/2019 | A | PASS |
Brandon Shaw
|
|
|
Insulation- OK to cover...
|
BLD-Framing/Rough-in | 7/1/2019 | 7/2/2019 | 7/2/2019 | A | PASS |
Brandon Shaw
|
|
|
Brian Phone #: ###-####
|
BLD-Wall Bracing | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | PASS |
Brandon Shaw
|
|
|
Interior shear panels to be installed before framing rough-in...
|
Routing - MECHANICAL | 6/24/2019 | | 6/24/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
Inspection Record Card- Bld | | | 5/1/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/1/2019 | | DONE |
|
|
|
|
BLD-Foundation | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PART |
Tony Young
|
|
|
Dustin-stem wall Phone #: ###-####,, work in progress,, missed layout on footings in some areas,, dowelled in and re-pour with wall ok
|
BLD-Footing | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Dave Hannah
|
|
|
Dustin Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/12/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 4/10/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 4/10/2019 | | DONE |
|
|
|
plan mod approved
|
Plan assigned to (JAB) Josh | 4/5/2019 | 4/5/2019 | 4/9/2019 | | PASS |
Josh Bogle
|
|
|
4/11 modification, ePlan - needs updated engineering
|
Routing - PLAN CHECK | 4/5/2019 | | 4/9/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2019 | | DONE |
Josh Bogle
|
|
|
one hour Plan Review fee
|
Routing - MECHANICAL | 4/5/2019 | | 4/8/2019 | | PASS |
Troy James
|
|
|
|
Plan Reviewer's activity | | | 4/5/2019 | | DONE |
Josh Bogle
|
|
|
pre-reviewed - e-mailed applicant to send me calc pages
|
Routing - PLANNING | 4/5/2019 | | 4/5/2019 | | PASS |
Ted Vanegas
|
|
|
|
Routing Walk-In (BLD) | 3/29/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Josh Bogle
|
|
|
Brian the GC - need plan mod
|
Plan Modification Accepted | | | 3/29/2019 | | DONE |
|
|
|
Brian the GC came into the office. Foundation was over the setbacks. New plans must be submitted.
|
Issue PAID IN FULL permit | | | 2/15/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/15/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 12/12/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 11/21/2018 | 11/21/2018 | 12/12/2018 | | PASS |
Josh Bogle
|
|
|
11/27 addition, ePlan - 1st done
|
Routing - PLAN CHECK | 12/12/2018 | | 12/12/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/12/2018 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 12/12/2018 | | DONE |
|
|
|
NEED
MET GC
Met
RP (PARCEL OWNER SEE EMAIL IN ESC DOCS)
|
Routing - PLAN CHECK | 11/21/2018 | | 11/27/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 11/27/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 11/21/2018 | | 11/26/2018 | | PASS |
Ted Vanegas
|
|
|
|
Routing - MECHANICAL | 11/26/2018 | | 11/26/2018 | | PASS |
Troy James
|
|
|
|
Plan Reviewer's activity | | | 11/26/2018 | | DONE |
Josh Bogle
|
|
|
returned to applicant for download of more information, per applicant request - no Plan Review has been done yet
|
Plans ACCEPTED BY PLAN TECH | | | 11/21/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/21/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/21/2018 | | DONE |
|
|
|
|
Application received | | | 11/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 20 2018 5:14PM
|
Application received | | 4/5/2019 | | | |
Josh Bogle
|
|
|
plan mod accepted in e plan by GF
|