Second Notice | | 3/21/2019 | 3/18/2019 | | DONE |
|
|
|
This permit finaled on the web by Caloub Huttash
|
First Notice | | 3/2/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12
|
Print Occupancy Form | | | 2/20/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/20/2019 | | DONE |
|
|
|
|
BLD-Final | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Dave Hannah
|
|
|
Please call Jared1/2 hour prior to inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
FIRE-Final Inspection | 2/18/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
Request Fire Final concurrent with Fire Alarm and Sprinkler Finals 7:30 am Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Ceiling Grid Inspection | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner ok after elec
|
BLD-Framing/Rough-in | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
Print Occupancy Form | | | 1/7/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/7/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 12/13/2018 | 12/13/2018 | 1/4/2019 | | PASS |
Joe Bruce
|
|
|
*(1st Rev Comp) 12/28 (L3) - Idaho Trust, ePlan (DR, Bldg)
|
Routing - PLAN CHECK | 1/2/2019 | | 1/4/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/4/2019 | | DONE |
|
|
|
MET (CALOUB@RUSSCORP.COM)
NEED
GC
Rev cert of val
|
Routing - Design Review | 1/2/2019 | | 1/3/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Plan resubmittals received | | | 1/2/2019 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 12/31/2018 | 1/3/2019 | 12/31/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 12/13/2018 | 12/13/2018 | 12/31/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 12/31/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 12/31/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 12/13/2018 | | 12/28/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing - Addressing | 12/13/2018 | | 12/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - Design Review | 12/13/2018 | | 12/14/2018 | | FAIL |
Katelyn Menuge
|
|
|
Weather protection does not meet DR requirements.
|
Routing - PUBLIC WORKS | 12/13/2018 | | 12/13/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 12/10/2018 | | PASS |
|
|
|
|
Intake Approval | | | 11/26/2018 | | FAIL |
Michael Hanson
|
|
|
Provide planning and zoning approval letter for exterior work (awning, door, etc...).
Provide fire extinguisher locations.
Provide wall bracing information (how will new walls be secured).
|
Application received | | | 11/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 21 2018 12:16PM
|