BLD-Final | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
DOC - Permit Finaled | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | NR |
Brandon Shaw
|
|
|
House should be open. Please call with any questions.
Thanks! Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Energy code compliance | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Energy code compliance | 7/18/2019 | 7/19/2019 | 7/19/2019 | A | FAIL |
Jim Storey
|
|
|
Hi, Need an energy inspection for the storage area above detached garage. Thank you Phone #: ###-#### Inspection requested via web by Steve Hanson missing vappor barrior on walls with attic exposer.
|
BLD-Energy code compliance | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PART |
Brandon Shaw
|
|
|
Garage only...
|
BLD-Framing/Rough-in | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Brandon Shaw
|
|
|
Living space above garage, framing rough-in...
|
CHANGE STATUS TO (ISS) | | | 7/15/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 7/11/2019 | | |
|
|
|
|
Telephone call | | | 7/11/2019 | | DONE |
|
|
|
called Kim to let know plan mod was ready and how much was owed-lef t message on her cell
|
Permit Ready to Issue | | | 7/11/2019 | | DONE |
|
|
|
plan mod so please do not re issue
|
Plan assigned to (BJM) | 7/2/2019 | 7/2/2019 | 7/10/2019 | | DONE |
Brian McGowan
|
|
|
plan mod
|
Routing - PLAN CHECK | 7/2/2019 | | 7/10/2019 | | PASS |
Brian McGowan
|
|
|
plan mod
|
Case Summary (BLD) | | | 7/10/2019 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLANNING | 7/2/2019 | | 7/5/2019 | | PASS |
Ted Vanegas
|
|
|
|
Routing - PUBLIC WORKS | 7/2/2019 | | 7/2/2019 | | PASS |
Morgan Webb
|
|
|
|
Plan Modification Accepted | | | 7/2/2019 | | DONE |
|
|
|
plan mod-adding toilet, sink & w/d hoookups-asigned and took to Brian McGowan
|
BLD-Framing/Rough-in | 6/25/2019 | 6/26/2019 | 6/26/2019 | A | FAIL |
Tony Young
|
|
|
framing reinspection and energy for garage. Power and vent have been removed from area above garage. Phone #: ###-#### Inspection requested via web by Steve Hanson/// need review set of plans from the city to reflect as built on garage floor plan with fixtures as well as electrical,, needs re-inspection on trades after as built approvals from city review.
|
BLD-Framing/Rough-in | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, SWO issued on upper garage area,, components are in for an Accessory dwelling unit (ADU), electrical, plumbing, etc, ,,remove or get approval,, lower area of garage needs fur downs if allowed to keep.. also need to verify mechanical has been looked at.. need to justify how the 1 hour seperation will be made if occupancy seperation is allowed.. ok to insulate lower area in garage if desired
|
BLD-Framing/Rough-in | 6/4/2019 | 6/5/2019 | 6/5/2019 | P | NR |
Tony Young
|
|
|
We need a framing/rough-in inspection for the detached garage please. Thank you Phone #: ###-#### Inspection requested via web by Steve Hanson,,, needs trades 1st
|
BLD-Framing/Rough-in | 5/17/2019 | 5/17/2019 | 5/17/2019 | P | PASS |
Brandon Shaw
|
|
|
Correctiions SAT...
|
BLD-Energy code compliance | 5/16/2019 | 5/16/2019 | 5/17/2019 | P | PEND |
Brandon Shaw
|
|
|
No ceiling cover- need Truss Engineering
|
BLD-Framing/Rough-in | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, correction notice posted,, house only
|
BLD-Wall Bracing | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, garage ok
|
BLD-Wall Bracing | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Foundation | 3/26/2019 | 3/26/2019 | 3/26/2019 | A | PART |
Tony Young
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro,, garage walls,, work in progress
|
BLD-Footing | 3/22/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Tony Young
|
|
|
As late as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes,, garage footings ok
|
BLD-Foundation | 3/8/2019 | 3/8/2019 | 3/8/2019 | A | PASS |
Dave Hannah
|
|
|
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | PART |
Tony Young
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro ,, grade footings on north side,, will need compaction reports and means to have the footing below grade on the west side
|
BLD-Foundation | 2/18/2019 | 2/19/2019 | 2/19/2019 | A | PART |
Tony Young
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro.. basement wall,, work in progress,, also planter
|
BLD-Footing | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | PART |
Tony Young
|
|
|
Wes Phone #: ###-####,, basement footing,, work in progress,, needs to be 12" thick
|
OVERRIDE | | | 2/6/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 2/4/2019 | 2/4/2019 | 2/6/2019 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 2/4/2019 | | 2/6/2019 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 2/6/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 2/6/2019 | | DONE |
|
|
|
plan mod approved
|
Telephone call | | | 2/6/2019 | | DONE |
|
|
|
Left voicemail for Kim to inform her the plan mod is approved and what fees are due.
|
CHANGE STATUS TO (ISS) | | | 2/6/2019 | | DONE |
|
|
|
plan mod
|
Plan Modification Accepted | | | 2/4/2019 | | DONE |
|
|
|
Chaning the foundation/ adding frost wall to the front.
Turned in two copies of sheet 3 foundation
|
Issue PAID IN FULL permit | | | 1/14/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/11/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 11/26/2018 | 11/26/2018 | 1/11/2019 | | DONE |
Brian McGowan
|
|
|
12/03 HERS Rating:Expedited Review
NO ADU WAS PERMITTED WITH THIS PERMIT
(Sheet 14 ELE PLANS: Garage upstairs electrical plan: Add notes about 220 for ADU,(ADU will be applied for in a different permit))
|
Meeting | | | 1/11/2019 | | DONE |
|
|
|
per brian value for adu to be taken out. owners are no longer having adu over the garage
|
Routing - PLAN CHECK | 1/11/2019 | | 1/11/2019 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 1/11/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 1/11/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/11/2019 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2019 | | DONE |
|
|
|
Left voicemail for Kim to inform her that the permit is ready and what fees are due.
|
Plan resubmittals received | | | 1/10/2019 | | DONE |
|
|
|
resubmittals recieved 2 sets of calcs-took to Brian McGowan
|
Routing - PLAN CHECK | 1/10/2019 | | 1/10/2019 | | FAIL |
Brian McGowan
|
|
|
Did not include Kaleb Jones engineering calculations in the resubmittal documents
|
Routing - PLAN CHECK | 1/9/2019 | | 1/9/2019 | | FAIL |
Brian McGowan
|
|
|
Need truss layouts as noted from plans and engineer's calculations.
|
Plan resubmittals received | | | 1/2/2019 | | DONE |
|
|
|
Two copies of each 1st fl framing, basement plan, 2nd floor framing plan, 2nd floor shear plan, roof plan, wall sections, electrcial plans and garage. Stamped and taken to plan reviewer.
|
Telephone call | | | 12/5/2018 | | DONE |
|
|
|
emailed Mike S to see about the PRK impact fees-gave him the dmeo permit # and asked him to check into it and see if the fees need removed
|
1st review completed | | | 12/5/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 12/3/2018 | | 12/4/2018 | | FAIL |
Brian McGowan
|
|
|
Cannot defer truss layout, missing beam sizes, point loads from girder trusses, etc.
|
Routing - MECHANICAL | 11/26/2018 | | 12/3/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 11/26/2018 | 11/29/2018 | 11/27/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 11/26/2018 | | 11/27/2018 | | PASS |
Ted Vanegas
|
|
|
|
Routing - Addressing | 11/26/2018 | | 11/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/26/2018 | | 11/26/2018 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/26/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/26/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/26/2018 | | PASS |
|
|
|
|
Application received | | 11/26/2018 | | | |
|
|
|
|