BLD-Final | 6/19/2019 | 6/20/2019 | 6/24/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.87
|
PubWorks Occupancy Approval | 6/20/2019 | 6/20/2019 | 6/20/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Other | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
BLD-Framing/Rough-in | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 3/4/2019 | 3/4/2019 | 3/4/2019 | P | PART |
Brandon Shaw
|
|
|
1st floor only...
|
BLD-Foundation | 1/16/2019 | 1/17/2019 | 1/17/2019 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Foundation | 1/14/2019 | 1/15/2019 | 1/15/2019 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell Inspection cancelled via mobile web on Tuesday, January 15, 2019.
|
BLD-Footing | 1/14/2019 | 1/14/2019 | 1/14/2019 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
PubWorks Subgrade Approval | 1/14/2019 | 1/14/2019 | 1/14/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 12/28/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/28/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 12/17/2018 | 12/20/2018 | 12/17/2018 | | PASS |
Eric Bilimoria
|
|
|
|
OVERRIDE | | | 12/14/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 12/14/2018 | 12/14/2018 | 12/14/2018 | | DONE |
|
|
|
|
Routing - FIRE | 12/14/2018 | 12/14/2018 | 12/14/2018 | | PASS |
Lee G Meredith
|
|
|
Plans passed review. An NFPA 13D fire sprinkler system is being provided, as noted on drawings A0.0 and A0.1.
|
Routing PW Grading-Hillside | 12/14/2018 | | 12/14/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
1st review completed | | | 12/14/2018 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/14/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/14/2018 | | 12/14/2018 | | PASS |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 12/14/2018 | | 12/14/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/14/2018 | | 12/14/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 12/14/2018 | | 12/14/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/14/2018 | | 12/14/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 12/14/2018 | | 12/14/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP listed. Site preparation inspection required.
|
Plans ACCEPTED BY PLAN TECH | | | 12/14/2018 | | DONE |
|
|
|
|
Intake Approval | | | 12/14/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/14/2018 | | DONE |
|
|
|
|
Application received | | | 11/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 27 2018 11:30AM
|