Third Notice | | 5/12/2020 | 5/13/2020 | | DONE |
|
|
|
This permit finaled on the web by Ian Franklin
|
Second Notice | | 4/13/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020
|
First Notice | | 3/28/2020 | 4/3/2020 | | DONE |
|
|
|
mailed 4-6-2020
|
Permanent Occupancy | | | 3/18/2020 | | DONE |
|
|
|
|
BLD-Final | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | PASS |
Mike Jordan
|
|
|
Ian Phone #: ###-####
|
PubWorks Occupancy Approval | 3/17/2020 | 3/17/2020 | 3/17/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | NR |
Jim Storey
|
|
|
Pierre Phone #: ###-#### need card signed pw and p$z
|
Zoning Approval | 3/16/2020 | 3/16/2020 | 3/16/2020 | | PASS |
Katelyn Menuge
|
|
|
Final
|
FIRE-Final Inspection | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Ian Phone #: ###-####
|
BLD-Framing/Rough-in | 2/4/2020 | 2/5/2020 | 2/5/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Foundation | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | CANC |
Mike Jordan
|
|
|
drywall inspections BLD18-04286 Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Other | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | PASS |
Mike Jordan
|
|
|
drywall inspections BLD18-04286 Phone #: ###-#### Inspection requested via web by Glen Farrell. 1st. and 2nd. layers.
|
BLD-Footing | 9/18/2019 | 9/19/2019 | 9/19/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Glen Farrell
|
Issue PAID IN FULL permit | | | 5/17/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/17/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/15/2019 | | DONE |
|
|
|
informed Kraig I would work on the fees, but to please let me know what the trades should be for each unit (gave the full project amount on those) also informed he we still need ACHD.
|
Expiration Notice | 4/30/2019 | 5/21/2019 | 4/30/2019 | | DONE |
Brittany Hill
|
|
|
|
Routing - FIRE | 4/4/2019 | 4/4/2019 | 4/9/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Final review 04.08.2019.pdf uploaded
|
Plan assigned to (CJW) | 12/7/2018 | 12/13/2018 | 4/9/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 01/10/18 (new - 25 days) (eplan - 28 sheets) Stor-it Self Storage Bldg 3 (routed to staff)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/9/2019 | | DONE |
|
|
|
MET KRAIG@FOREGEBUILDINGS.COM
NEED
ACHD (SEE BLD19-04286 DOCUMENTS)
MET
GC FORM
REVISED VALUE
|
Routing PW Drainage | 4/4/2019 | | 4/5/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 4/4/2019 | | 4/4/2019 | | PASS |
Carl Westfall
|
|
|
Resubmittal review approved
|
Plan resubmittals received | | | 4/4/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/4/2019 | | DONE |
|
|
|
Failed resubmittal plan intake
|
Routing - Design Review | 4/4/2019 | | 4/4/2019 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 4/3/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/12/2019 | 1/15/2019 | 1/14/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/13/2018 | | 1/12/2019 | | FAIL |
Carl Westfall
|
|
|
|
1st review completed | | | 1/12/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/12/2019 | | DONE |
|
|
|
|
Routing - FIRE | 12/7/2018 | 12/13/2018 | 1/9/2019 | | FAIL |
Mark Scharfen
|
|
|
Attached IFC Fire Code Review Comments and emailed architecht.
|
Routing Off Site - STRUCTURAL | 12/13/2018 | | 12/26/2018 | | PASS |
Carl Westfall
|
|
|
Sidney Gold (KPFF)
|
Routing PW Drainage | 12/13/2018 | | 12/18/2018 | | FAIL |
Brian Murphy
|
|
|
need 1.5 feet of sand
|
Routing PW Solid Waste | 12/13/2018 | | 12/14/2018 | | PASS |
Evan Carpenter
|
|
|
Approved for commercial cart service.
|
Routing - Design Review | 12/13/2018 | | 12/14/2018 | | FAIL |
Andrea Tuning
|
|
|
45 degree parking stalls are required to be a minimum of 9-feet wide and 20-feet 5-inches in depth.
Pave all parking and drive aisles on 19 North Allumbaugh Street and 55 North Allumbaugh Street.
|
Routing - PLANNING | 12/13/2018 | | 12/13/2018 | | PASS |
David Moser
|
|
|
See DRH17-00528
|
Routing - Addressing | 12/13/2018 | | 12/13/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/13/2018 | | 12/13/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 12/13/2018 | | 12/13/2018 | | PASS |
Andy J. Long
|
|
|
ESC permit VOID. See main ESC permit for storage complex, ESC18-01667
|
Routing PW Street Lights | 12/13/2018 | | 12/13/2018 | | PASS |
Tom Marshall
|
|
|
|
Intake Approval | | | 12/7/2018 | | PASS |
Michael Hanson
|
|
|
Prescreen approved by M_H.
|
Intake Approval | | | 12/3/2018 | | FAIL |
Michael Hanson
|
|
|
The structural calculation did not upload properly. Please try to upload again.
S1 and ESC-1 are missing the stamp signed and dated.
|
Application received | | | 11/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 27 2018 1:06PM
|