Permit Information
Permit NumberBLD18-04291
StatusFinaled
Name FORGE BUILDING COMPANY LLC
Site Address 55 N ALLUMBAUGH ST
Project NameStor-It Self Storage Bldg 5
Customer Number 
ePlanReviewYes
Description
(STOR-IT SELF STORAGE – BUILDING #5) (DRH17-00528) This building does not have a fire sprinkler system. To construct a new 3,543 square foot self-storage building with 11 individual self-storage units. One unit will be accessible to the disabled. This building is one of five on this site. Work is to include concrete footings; concrete slab on grade thickened at roll-up doors, at exterior walls, and at the 3 hour fire wall; steel stud bearing and shear walls; steel shear panels; anchors post-installed in hardened concrete; steel exterior siding; steel roof purlins; steel strap roof braces; steel drag struts; steel roof panels; metal gutters; a 2-hr property line wall; a 3-hr fire wall; and roll-up doors. Special Inspection is required for soils, for concrete, for structural steel (including welding and bolting), and for post-installed anchors in hardened concrete. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 5/17/20205/13/2020 DONE
This permit finaled on the web by Ian Franklin
First Notice 4/4/20205/7/2020 DONE
mailed 5-8-2020
Permanent Occupancy  3/24/2020 DONE
BLD-Final3/18/20203/18/20203/18/2020PPASS
DetailsMike Jordan
Ian Phone #: ###-####. Ok for perm occ.
BLD-Final3/16/20203/17/20203/17/2020AFAIL
DetailsMike Jordan
Ian Phone #: ###-####. Complete fire caulking in stair towers.
PubWorks Occupancy Approval3/17/20203/17/20203/17/2020 DONE
DetailsTiffany Lowery
BLD-Final3/13/20203/16/20203/16/2020ANR
DetailsJim Storey
Pierre Phone #: ###-#### need card signed pw and p$z
Zoning Approval3/16/20203/16/20203/16/2020 PASS
DetailsKatelyn Menuge
Final
FIRE-Final Inspection3/13/20203/13/20203/13/2020PPASS
DetailsTroy Cobbley
Life safety passed. Ian Phone #: ###-####
CHANGE STATUS TO (ISS)  3/13/2020 DONE
Permit was accidentally put in Finaled status. Needs to have a final BLD Inpsection for occupancy
Zoning Approval Temp3/3/20203/3/20203/3/2020 PASS
DetailsKatelyn Menuge
Temporary-Can have final when all site improvements are complete.
BLD-Final1/31/20202/3/20202/3/2020PNR
DetailsMike Jordan
Glen Phone #: ###-####
FIRE-Final Inspection1/31/20202/3/20202/3/2020AFAIL
DetailsTroy Cobbley
Failed based on noted deficiencies: secondary gate needed opticon installed., tested and pavement, primary gate needed opticon tested and pavement installed, clearanced between
AC unit ballard and fence was less than 20 foot required clearance north end of blding 2, site and blding addrss numbers/letters need to be provided as per discussion, provide most up to date review comments.




Glen Phone #: ###-####
BLD-Footing8/21/20198/22/20198/22/2019APASS
DetailsMike Jordan
footing and rebar Phone #: ###-#### Inspection requested via web by Glen Farrell
BLD-Footing7/18/20197/19/20197/19/2019PCANC
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Glen Farrell
Issue PAID IN FULL permit  5/17/2019 DONE
Print Occupancy Form  5/17/2019 DONE
Telephone call  5/15/2019 DONE
informed Kraig I would work on the fees, but to please let me know what the trades should be for each unit (gave the full project amount on those) also informed he we still need ACHD.
Expiration Notice5/9/20195/31/20195/9/2019 DONE
DetailsBrittany Hill
Permit Ready to Issue  5/7/2019 DONE
MET KRAIG@FOREGEBUILDINGS.COM
NEED
ACHD (SEE BLD19-04286 DOCUMENTS)
MET
GC FORM
REVISED VALUE
CHANGE ISSUED DATE  5/7/2019 DONE
Routing - FIRE5/3/20195/3/20195/6/2019 PASS
DetailsMark Scharfen
IFC review completed 05.06.2019. Uploaded Rev_fire_05.06.2019.pdf. Passed review.
Plan assigned to (CJW)4/9/20194/9/20195/6/2019 PASS
DetailsCarl Westfall
(1st done) 01/10/18 (new - 25 days) (eplan - 26 sheets) Stor-it Self Storage Bldg 5 (routed to fire)
PLANS/APPL TAKEN TO FRONT DESK  5/6/2019 DONE
Plan resubmittals received  5/3/2019 DONE
Routing - PLAN CHECK5/3/2019 5/3/2019 PASS
DetailsCarl Westfall
Routing - FIRE4/9/20194/9/20194/9/2019 FAIL
DetailsMark Scharfen
IFC 2nd Review 04.09.2019.pdf uploaded and emailed to architect.
Plan resubmittals requested  4/9/2019 DONE
Routing - FIRE4/4/20194/4/20194/8/2019 FAIL
DetailsMark Scharfen
IFC Final review 04.08.2019.pdf
Plan assigned to (CJW)12/7/201812/13/20184/8/2019 PASS
DetailsCarl Westfall
(1st done) 01/10/18 (new - 25 days) (eplan - 26 sheets) Stor-it Self Storage Bldg 5 (routed to staff)
PLANS/APPL TAKEN TO FRONT DESK  4/8/2019 DONE
Pulled back to resolve fire access issues
Permit Ready to Issue  4/8/2019 DONE
do not issue until Adele gives the ok
NEED
ACHD
GC FORM
REVISED VALUE
Routing PW Drainage4/4/2019 4/5/2019 PASS
DetailsBrian Murphy
Routing - PLAN CHECK4/4/2019 4/4/2019 PASS
DetailsCarl Westfall
Resubmittal review approved
Routing - Design Review4/4/2019 4/4/2019 PASS
DetailsAndrea Tuning
Plan resubmittals received  4/4/2019 DONE
Plan resubmittals received  4/3/2019 DONE
Plan resubmittals requested  4/3/2019 DONE
Failed plan intake and IBC resubmittal review
Route to Impact Fee Review1/11/20191/14/20191/11/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK12/13/2018 1/10/2019 FAIL
DetailsCarl Westfall
Revised drawings required
1st review completed  1/10/2019 DONE
Plan resubmittals requested  1/10/2019 DONE
Routing - FIRE12/7/201812/13/20181/9/2019 FAIL
DetailsMark Scharfen
Attached IFC Fire Code Review and emailed architect.
Routing Off Site - STRUCTURAL12/13/2018 12/26/2018 PASS
DetailsCarl Westfall
Sidney Gold (KPFF)
Routing PW Drainage12/13/2018 12/18/2018 FAIL
DetailsBrian Murphy
need 1.5 feet
Routing PW Solid Waste12/13/2018 12/14/2018 PASS
DetailsEvan Carpenter
Approved for commercial cart service.
Routing - Design Review12/13/2018 12/14/2018 FAIL
DetailsAndrea Tuning
45 degree parking stalls are required to be a minimum of 9-feet wide and 20-feet 5-inches in depth.

Pave all parking and drive aisles on 19 North Allumbaugh Street and 55 North Allumbaugh Street.
Routing - PLANNING12/13/2018 12/13/2018 PASS
DetailsDavid Moser
See DRH17-00528
Routing - Addressing12/13/2018 12/13/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/13/2018 12/13/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment12/13/2018 12/13/2018 PASS
DetailsAndy J. Long
ESC permit VOID. See main ESC permit for storage complex, ESC18-01667
Routing PW Street Lights12/13/2018 12/13/2018 PASS
DetailsTom Marshall
Intake Approval  12/7/2018 PASS
DetailsMichael Hanson
Prescreen approved by M_H.
Intake Approval  12/3/2018 FAIL
DetailsMichael Hanson
The structural calculation did not upload properly. Please try to upload again.
S1 and ESC-1 are missing the stamp signed and dated.
Application received  11/27/2018 DONE
Application submitted via PDS Online on Nov 27 2018 1:21PM
PubWorks Occupancy Approval1/31/20201/31/2020  DONE