Second Notice | | 5/17/2020 | 5/13/2020 | | DONE |
|
|
|
This permit finaled on the web by Ian Franklin
|
First Notice | | 4/4/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020
|
Permanent Occupancy | | | 3/24/2020 | | DONE |
|
|
|
|
BLD-Final | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Mike Jordan
|
|
|
Ian Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | FAIL |
Mike Jordan
|
|
|
Ian Phone #: ###-####. Complete fire caulking in stair towers.
|
PubWorks Occupancy Approval | 3/17/2020 | 3/17/2020 | 3/17/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | NR |
Jim Storey
|
|
|
Pierre Phone #: ###-#### need card signed pw and p$z
|
Zoning Approval | 3/16/2020 | 3/16/2020 | 3/16/2020 | | PASS |
Katelyn Menuge
|
|
|
Final
|
FIRE-Final Inspection | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Ian Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 3/13/2020 | | DONE |
|
|
|
Permit was accidentally put in Finaled status. Needs to have a final BLD Inpsection for occupancy
|
Zoning Approval Temp | 3/3/2020 | 3/3/2020 | 3/3/2020 | | PASS |
Katelyn Menuge
|
|
|
Temporary-Can have final when all site improvements are complete.
|
BLD-Final | 1/31/2020 | 2/3/2020 | 2/3/2020 | P | NR |
Mike Jordan
|
|
|
Glen Phone #: ###-####
|
FIRE-Final Inspection | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | FAIL |
Troy Cobbley
|
|
|
Failed based on noted deficiencies: secondary gate needed opticon installed., tested and pavement, primary gate needed opticon tested and pavement installed, clearanced between AC unit ballard and fence was less than 20 foot required clearance north end of blding 2, site and blding addrss numbers/letters need to be provided as per discussion, provide most up to date review comments.
Glen Phone #: ###-####
|
BLD-Footing | 8/21/2019 | 8/22/2019 | 8/22/2019 | A | PASS |
Mike Jordan
|
|
|
footing and rebar Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Footing | 7/18/2019 | 7/19/2019 | 7/19/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Glen Farrell
|
Issue PAID IN FULL permit | | | 5/17/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/17/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/15/2019 | | DONE |
|
|
|
informed Kraig I would work on the fees, but to please let me know what the trades should be for each unit (gave the full project amount on those) also informed he we still need ACHD.
|
Expiration Notice | 5/9/2019 | 5/31/2019 | 5/9/2019 | | DONE |
Brittany Hill
|
|
|
|
Permit Ready to Issue | | | 5/7/2019 | | DONE |
|
|
|
MET KRAIG@FOREGEBUILDINGS.COM
NEED
ACHD (SEE BLD19-04286 DOCUMENTS)
MET
GC FORM
REVISED VALUE
|
CHANGE ISSUED DATE | | | 5/7/2019 | | DONE |
|
|
|
|
Routing - FIRE | 5/3/2019 | 5/3/2019 | 5/6/2019 | | PASS |
Mark Scharfen
|
|
|
IFC review completed 05.06.2019. Uploaded Rev_fire_05.06.2019.pdf. Passed review.
|
Plan assigned to (CJW) | 4/9/2019 | 4/9/2019 | 5/6/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 01/10/18 (new - 25 days) (eplan - 26 sheets) Stor-it Self Storage Bldg 5 (routed to fire)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/3/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/3/2019 | | 5/3/2019 | | PASS |
Carl Westfall
|
|
|
|
Routing - FIRE | 4/9/2019 | 4/9/2019 | 4/9/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 2nd Review 04.09.2019.pdf uploaded and emailed to architect.
|
Plan resubmittals requested | | | 4/9/2019 | | DONE |
|
|
|
|
Routing - FIRE | 4/4/2019 | 4/4/2019 | 4/8/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC Final review 04.08.2019.pdf
|
Plan assigned to (CJW) | 12/7/2018 | 12/13/2018 | 4/8/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 01/10/18 (new - 25 days) (eplan - 26 sheets) Stor-it Self Storage Bldg 5 (routed to staff)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2019 | | DONE |
|
|
|
Pulled back to resolve fire access issues
|
Permit Ready to Issue | | | 4/8/2019 | | DONE |
|
|
|
do not issue until Adele gives the ok
NEED
ACHD
GC FORM
REVISED VALUE
|
Routing PW Drainage | 4/4/2019 | | 4/5/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 4/4/2019 | | 4/4/2019 | | PASS |
Carl Westfall
|
|
|
Resubmittal review approved
|
Routing - Design Review | 4/4/2019 | | 4/4/2019 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 4/4/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/3/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/3/2019 | | DONE |
|
|
|
Failed plan intake and IBC resubmittal review
|
Route to Impact Fee Review | 1/11/2019 | 1/14/2019 | 1/11/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/13/2018 | | 1/10/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 1/10/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/10/2019 | | DONE |
|
|
|
|
Routing - FIRE | 12/7/2018 | 12/13/2018 | 1/9/2019 | | FAIL |
Mark Scharfen
|
|
|
Attached IFC Fire Code Review and emailed architect.
|
Routing Off Site - STRUCTURAL | 12/13/2018 | | 12/26/2018 | | PASS |
Carl Westfall
|
|
|
Sidney Gold (KPFF)
|
Routing PW Drainage | 12/13/2018 | | 12/18/2018 | | FAIL |
Brian Murphy
|
|
|
need 1.5 feet
|
Routing PW Solid Waste | 12/13/2018 | | 12/14/2018 | | PASS |
Evan Carpenter
|
|
|
Approved for commercial cart service.
|
Routing - Design Review | 12/13/2018 | | 12/14/2018 | | FAIL |
Andrea Tuning
|
|
|
45 degree parking stalls are required to be a minimum of 9-feet wide and 20-feet 5-inches in depth.
Pave all parking and drive aisles on 19 North Allumbaugh Street and 55 North Allumbaugh Street.
|
Routing - PLANNING | 12/13/2018 | | 12/13/2018 | | PASS |
David Moser
|
|
|
See DRH17-00528
|
Routing - Addressing | 12/13/2018 | | 12/13/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/13/2018 | | 12/13/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 12/13/2018 | | 12/13/2018 | | PASS |
Andy J. Long
|
|
|
ESC permit VOID. See main ESC permit for storage complex, ESC18-01667
|
Routing PW Street Lights | 12/13/2018 | | 12/13/2018 | | PASS |
Tom Marshall
|
|
|
|
Intake Approval | | | 12/7/2018 | | PASS |
Michael Hanson
|
|
|
Prescreen approved by M_H.
|
Intake Approval | | | 12/3/2018 | | FAIL |
Michael Hanson
|
|
|
The structural calculation did not upload properly. Please try to upload again.
S1 and ESC-1 are missing the stamp signed and dated.
|
Application received | | | 11/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 27 2018 1:21PM
|
PubWorks Occupancy Approval | 1/31/2020 | 1/31/2020 | | | DONE |
|
|
|
|