Letter of compliance/Occupancy | | | 7/22/2019 | | DONE |
|
|
|
|
BLD-Blower Door Test Results | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | DONE |
Tell Riley
|
|
|
3.2 ACH50 1701 @ 50 pa
|
BLD-Final | 7/12/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Tell Riley
|
|
|
as early as possible // Mack Phone #: ###-####
|
DOC - Permit Finaled | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 7/10/2019 | 7/12/2019 | 7/12/2019 | P | NR |
Tell Riley
|
|
|
Mac Phone #: ###-####//need blower door test completed and results posted//
|
BLD-Energy code compliance | 5/6/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
BLD-Framing/Rough-in | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Jim Sly
|
|
|
I would like to meet you onsite if possible to review any corrections.
Thanks, Drew Moorhouse McCarter-Moorhouse ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
BLD-Wall Bracing | 4/8/2019 | 4/9/2019 | 4/10/2019 | P | PASS |
Jim Sly
|
|
|
The plans are in the job mail box and the code is 1027. we are looking for a sheer inspection so we can cover the exterior.
Thanks, Drew Moorhouse McCarter-Moorhouse ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
BLD-Footing | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PASS |
Jim Sly
|
|
|
Plans are in the plan box and the code is 1027. Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
OVERRIDE | | | 3/20/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 12/5/2018 | 12/5/2018 | 3/20/2019 | | DONE |
Brian McGowan
|
|
|
1st review complete 12/18 sfd L1 paper - Corrections Required
|
Routing - PLAN CHECK | 3/7/2019 | | 3/20/2019 | | PASS |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2019 | | DONE |
|
|
|
|
Telephone call | | | 3/20/2019 | | DONE |
|
|
|
called Drew to let know permit is ready and how much is owed
|
Issue PAID IN FULL permit | | | 3/20/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/20/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/20/2019 | | DONE |
|
|
|
NEED
met-RP (ONE GIVEN IS EXPIRED)
NEED-PERMIT SIGNED AND SCANNED IN
|
Plan resubmittals received | | | 3/15/2019 | | DONE |
|
|
|
Resubmittalas received 2 sets of sheets A-102 & A--103-took to BJM
|
Routing - PLANNING | 3/8/2019 | | 3/8/2019 | | PASS |
Sue Cummings
|
|
|
SOS19-00022 approved / vacation of plat note. Meets setback now.
|
Plan Reviewer's activity | | | 3/7/2019 | | DONE |
Brian McGowan
|
|
|
Took site plans to Sue C. to have with the rest of the plans.
|
Plan resubmittals received | | | 3/7/2019 | | DONE |
|
|
|
Two copies of large sit plan and 8x11 site plan stamped and taken to plan reviewer
|
Plan Reviewer's activity | | | 3/5/2019 | | DONE |
Brian McGowan
|
|
|
David Moser took plans.
|
Routing - PUBLIC WORKS | | | 12/18/2018 | | PASS |
|
|
|
|
1st review completed | | | 12/18/2018 | | FAIL |
Brian McGowan
|
|
|
Will take back to Public Works to see why it isnt signed off. 12-18
|
Routing - PLAN CHECK | 12/12/2018 | | 12/18/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 12/10/2018 | | 12/12/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 12/5/2018 | | 12/10/2018 | | PASS |
Doug Chausow
|
|
|
|
Route to Impact Fee Review | 12/5/2018 | 12/8/2018 | 12/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 12/5/2018 | | DONE |
|
|
|
started online-had C_P void it in e plan
|
Intake Approval | | | 12/5/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/5/2018 | | DONE |
|
|
|
|
Application received | | | 12/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 3 2018 9:48AM
|
Routing - PLANNING | | | | | FAIL |
|
|
|
Does not meet the setback noted on the plat. Notified applicant 12/10/18 @ 4:00
|