BLD-Blower Door Test Results | 7/9/2019 | 7/9/2019 | 7/9/2019 | A | DONE |
Jim Storey
|
|
|
2.6
|
BLD-Blower Door Test Results | 6/13/2019 | 6/14/2019 | 6/19/2019 | A | NR |
Jim Storey
|
|
|
|
BLD-Final | 6/12/2019 | 6/13/2019 | 6/13/2019 | A | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-####
|
DOC - Permit Finaled | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Wall Bracing | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Mike Jordan
|
|
|
firewall in garage // Rusty Phone #: ###-####
|
BLD-Wall Bracing | 4/8/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Brandon Shaw
|
|
|
Need garage shear inspection... Work in progress...
|
BLD-Footing | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Jim Storey
|
|
|
derek Phone #: ###-####
|
BLD-Other | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Jim Storey
|
|
|
sofit- Gus Phone #: ###-####
|
BLD-Footing | 3/15/2019 | 3/18/2019 | 3/18/2019 | P | CANC |
Jim Storey
|
|
|
Derreck Phone #: ###-####
|
BLD-Energy code compliance | 3/11/2019 | 3/11/2019 | 3/11/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Rusty Cook
|
BLD-Framing/Rough-in | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-####
|
BLD-Wall Bracing | 2/21/2019 | 2/21/2019 | 2/21/2019 | P | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-####
|
BLD-Footing | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Jim Storey
|
|
|
Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/19/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/19/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 12/14/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 12/7/2018 | 12/7/2018 | 12/14/2018 | | DONE |
Jenny Nelson
|
|
|
12/20 sfd L1 ePlan. 1st complete, failed planning, specify garage header, changing to prescriptive energy provide info, wall bracing issues, foundation venting, crawl access
|
Routing - PLAN CHECK | 12/14/2018 | | 12/14/2018 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/14/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 12/12/2018 | | 12/12/2018 | | PASS |
Katelyn Menuge
|
|
|
|
1st review completed | | | 12/11/2018 | | FAIL |
Jenny Nelson
|
|
|
failed planning, specify garage header, changing to prescriptive energy provide info, wall bracing issues, foundation venting, crawl access
|
Routing - PLAN CHECK | 12/7/2018 | | 12/11/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 12/7/2018 | | 12/11/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 12/7/2018 | 12/10/2018 | 12/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 12/7/2018 | | 12/10/2018 | | PASS |
Doug Chausow
|
|
|
|
Plan assigned to (BJM) | 12/7/2018 | 12/7/2018 | 12/7/2018 | | DEFR |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | 12/7/2018 | | 12/7/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLANNING | 12/7/2018 | | 12/7/2018 | | FAIL |
Katelyn Menuge
|
|
|
Corrections Required
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/7/2018 | | DONE |
|
|
|
|
Intake Approval | | | 12/7/2018 | | PASS |
|
|
|
|
Application received | | | 12/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 5 2018 6:36AM
|
Intake Approval | | | 12/5/2018 | | FAIL |
|
|
|
Please label the rooms and which floor is what level on the floor plan. (New parcel number not in system yet.)
|