Permit Information
Permit NumberBLD18-04389
StatusFinaled
Name ESI
Site Address 139 E WARM SPRINGS AVE
Project NameRonald McDonald House Foundati
Customer NumberBLD19-00278, GRD18-00080
ePlanReviewYes
Description
(RONAL MCDONALD HOUSE) **Project Management-Ron Hill** FOUNDATION ONLY & UNDERGROUND WORK _ New Ronald McDonald House of approximately 40,000 square feet. GRADING & DRAINAGE APPROVED UNDER GRD18-00080. The new two story structure will provide 47 new guest rooms for families, lobby, administrative offices and support functions.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval5/18/20205/18/20205/18/2020 DONE
DetailsTiffany Lowery
First Notice4/24/20204/24/20205/7/2020 DONE
DetailsDave Hannah
mailed 5-8-2020
BLD-Final4/24/20204/27/20204/24/2020APASS
DetailsDave Hannah
DOC - Permit Finaled4/24/20204/24/20204/24/2020PPASS
DetailsDave Hannah
BLD-Final7/18/20197/18/20197/18/2019PPASS
DetailsDave Hannah
BLD-Concrete4/3/20194/4/20194/5/2019PPASS
DetailsDave Hannah
Section 3 (south side of Area B) vapor barrier and reinforcement under SOG. Special inspection will be complete by MTI for visual and concrete cylinders. Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Concrete3/26/20193/28/20193/28/2019PPASS
DetailsDave Hannah
Vapor barrier and reinforcement section 2 (east side of Area A and northeast corner of Area B). Concrete to be placed Friday morning at 5am MTI special inspection will be onsite. Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Concrete3/20/20193/21/20193/22/2019PPASS
DetailsDave Hannah
Placing concrete for SOG for first section of Area A. Concrete to be onsite 5am Friday morning with special inspection from MTI. Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Foundation3/5/20193/6/20193/6/2019APASS
DetailsDave Hannah
Stem wall Area B Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Foundation3/5/20193/7/20193/5/2019ACANC
DetailsDave Hannah
Stem wall all of Area B. Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
BLD-Footing2/27/20192/28/20192/28/2019APART
DetailsJim Sly
Placing concrete for footings on the north/northeast side of Area B and elevator stem walls in Area A. Pump to be onsite at 11am. We Phone #: ###-#### Inspection requested via web by Corey Hockersmith
OK pending MTI special inspection, tests and approvals.
BLD-Foundation2/22/20192/25/20192/25/2019APART
DetailsJim Sly
Concrete to be onsite at 11:00am. Phone #: ###-#### Inspection requested via web by Corey Hockersmith
Foundation walls at area A ( West 1/2 of Bldg) and Footings for Elevator Pit OK ..........Pending MTI special inspections, tests and approvals.
BLD-Footing2/15/20192/19/20192/19/2019APASS
DetailsDave Hannah
Please call in the morning if possible. Phone #: ###-#### Inspection requested via web by Corey Hockersmith
Inspection Record Card- Bld  2/19/2019 DONE
OVERRIDE  2/12/2019  
Issue PAID IN FULL permit  2/12/2019 DONE
Inspection Record Card- Bld  2/12/2019 DONE
Permit Ready to Issue  2/12/2019 DONE
MET
Need
GC
Rev cert of val
Routing - FIRE2/8/20192/8/20192/11/2019 PASS
DetailsErika Akin
Attached comments to case
Plan assigned to (CDM)12/10/201812/10/20182/11/2019 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK1/30/2019 2/11/2019 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL2/8/2019 2/11/2019 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  2/11/2019 DONE
Routing Off Site - STRUCTURAL1/30/2019 2/11/2019 FAIL
DetailsCarl D Madsen
Routing PW Drainage2/8/2019 2/8/2019 PASS
DetailsBrian Murphy
Routing - FIRE1/30/20191/30/20192/7/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - Erosion and Sediment2/6/2019 2/6/2019 PASS
DetailsAndy J. Long
VOID ESC permit. Site has active ESC permit ESC18-01432
Routing PW Drainage2/5/2019 2/5/2019 FAIL
DetailsBrian Murphy
NEED 3TO1 SLOPE ON WORKING
Route to Impact Fee Review1/31/20192/3/20192/1/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing PW Street Lights1/31/2019 1/31/2019 PASS
DetailsTom Marshall
Routing - FIRE12/10/201812/10/20181/17/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
1st review completed  1/17/2019 DONE
Routing Off Site - STRUCTURAL12/10/2018 12/28/2018 FAIL
DetailsCarl D Madsen
KPFF
Routing - PLAN CHECK12/10/2018 12/28/2018 PASS
DetailsCarl D Madsen
Routing PW Environmental12/10/2018 12/26/2018 PASS
DetailsTerry Alber
Disposers shown in schedule (D-1), but not on plans. No grease abatement shown. If disposers are installed, 1500-gallon, in-ground, grease interceptor is required. If no grease abatement is installed, no disposers are allowed in kitchen sinks.
Routing PW Geothermal12/10/2018 12/17/2018 PASS
DetailsJon R. Gunnerson
No connection to the City's geothermal heating district. If wanting a connection, contact Public Works at 208.608.7150
Routing PW Drainage12/10/2018 12/17/2018 FAIL
DetailsBrian Murphy
need swale 3 to 1
Routing - Design Review12/10/2018 12/14/2018 PASS
DetailsJosh Wilson
Routing - PLUMBING12/10/2018 12/11/2018 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - PLANNING12/10/2018 12/11/2018 PASS
DetailsDavid Moser
See DRH18-00483
Routing PW Street Lights12/10/2018 12/11/2018 FAIL
DetailsTom Marshall
Need 4 historic poles and meter cabinet on a street lighting plan.
Routing PW Solid Waste12/10/2018 12/11/2018 PASS
DetailsEvan Carpenter
Routing - Addressing12/10/2018 12/10/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/10/2018 12/10/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment12/10/2018 12/10/2018 PASS
DetailsMichael Zawacki
Site prep inspection required.
Intake Approval  12/7/2018 PASS
Application received  12/6/2018 DONE
Application submitted via PDS Online on Dec 6 2018 2:29PM
BLD-Final6/24/20196/24/2019 P 
DetailsDave Hannah
cory Phone #: ###-####
Routing PW Sewer Design12/10/2018   PASS
DetailsDeAnn Brown