BLD-Final | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 9/16/2019 | 9/18/2019 | 9/18/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Blower Door Test Results | 9/9/2019 | 9/9/2019 | 9/9/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4
|
BLD-Final | 9/3/2019 | 9/9/2019 | 9/9/2019 | A | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Energy code compliance | 7/3/2019 | 7/5/2019 | 7/5/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 6/28/2019 | 7/2/2019 | 7/2/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PART |
Tell Riley
|
|
|
Rudy Phone #: ###-####//nailing ok per plans// add hold downs at corner windows (Front) per plans//check at framing//
|
BLD-Foundation | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 3/21/2019 | 3/21/2019 | 3/21/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 3/20/2019 | 3/20/2019 | 3/20/2019 | P | NR |
Brandon Shaw
|
|
|
Need soil subgrade submitted and approved by PW...
|
Issue PAID IN FULL permit | | | 2/27/2019 | | DONE |
|
|
|
emailed Blackrock
|
Inspection Record Card- Bld | | | 2/27/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 2/22/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 12/7/2018 | 12/7/2018 | 2/22/2019 | | DONE |
Brian McGowan
|
|
|
12/20 sfd L1 ePlan - 1st review complete - Corrections Required
|
Routing - PLAN CHECK | 2/22/2019 | | 2/22/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/22/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 2/22/2019 | | DONE |
|
|
|
met
|
Routing - FIRE | 12/21/2018 | 12/21/2018 | 12/26/2018 | | PASS |
Lee G Meredith
|
|
|
Fire sprinklers are not required.
|
1st review completed | | | 12/20/2018 | | FAIL |
Brian McGowan
|
|
|
Need code references and Portal Frame detail updated to 2015 IRC
|
Routing - PLAN CHECK | 12/7/2018 | | 12/20/2018 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 12/7/2018 | 12/10/2018 | 12/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 12/7/2018 | | 12/10/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 12/7/2018 | | 12/10/2018 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 12/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 7 2018 11:38AM
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/2018 | | DONE |
|
|
|
|
Intake Approval | | | 12/7/2018 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 12/7/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/7/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 12/7/2018 | | 12/7/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | 12/7/2018 | | 12/7/2018 | | PASS |
Angela Hardy
|
|
|
|