Third Notice | | 12/1/2019 | 12/4/2019 | | DONE |
|
|
|
This permit finaled on the web by Robin Baum
|
Second Notice | | 11/8/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | | 9/30/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1
|
Telephone call | | | 9/20/2019 | | |
|
|
|
Building was given a "final" accidently but it needs mechanical and MEC19-01208 was attached to the wrong project when it should of been attached to this building, talked to Plan Reviewer JG and required signatures were clarify.
Per Brian Scole the mechanical needs a rough-in and final before this building gets final OCC
|
Inspection Record Card- Bld | | | 9/20/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/20/2019 | | DONE |
|
|
|
|
BLD-Aging Inspection | 9/18/2019 | 9/18/2019 | 9/18/2019 | | PASS |
Tell Riley
|
|
|
permit shows passed but no occupancy issued
|
BLD-Final | 4/26/2019 | 4/29/2019 | 5/7/2019 | P | PASS |
Jim Sly
|
|
|
please go after 3pm-Mike Phone #: ###-####
|
FIRE-Final Inspection | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. Mike Phone #: ###-####
|
FIRE-Final Inspection | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | FAIL |
Troy Cobbley
|
|
|
Install exit signs per approved plans or get plan review approval to relocate or remove.
Mike Phone #: ###-####
|
BLD-Final | 4/24/2019 | 4/25/2019 | 4/25/2019 | P | NR |
Jim Sly
|
|
|
after 3 // Mike Phone #: ###-#### See previos notes
|
FIRE-Final Inspection | 4/24/2019 | 4/25/2019 | 4/25/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide city approved plans and small documents and repair or remove the west exit door exit sign.
Mike Phone #: ###-####
|
BLD-Final | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | NR |
Jim Sly
|
|
|
request after 3pm // Mike Phone #: ###-#### Need Fire final. Verify if Mech permit is required. Showing valuation of 1200.00
|
FIRE-Final Inspection | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning when there are no customers. Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 2/19/2019 | 2/21/2019 | 2/21/2019 | A | PASS |
Jim Sly
|
|
|
Mike-PLM & ELE have been approved Phone #: ###-####
|
BLD-Framing/Rough-in | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | CANC |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PART |
Jim Sly
|
|
|
please call 15 min for access-Devin Phone #: ###-#### Framing appears OK......Electr, Plumb and Mech rough-ins not done yet. OK to pass when above items done.
|
Print Occupancy Form | | | 1/17/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/17/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/11/2018 | 12/11/2018 | 1/9/2019 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/14 L1 First Class Denture TI ePlan
|
Routing - PLAN CHECK | 1/9/2019 | | 1/9/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 1/9/2019 | | 1/9/2019 | | PASS |
Doug Chausow
|
|
|
Suite and Sign off in Tidemark vanilla permit BLD19-00100
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/9/2019 | | DONE |
|
|
|
MET
NEED
REVISED VALUE
MET
GC FORM
|
Route to Impact Fee Review | 12/14/2018 | 12/17/2018 | 12/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/11/2018 | | 12/14/2018 | | FAIL |
Javier Guzman
|
|
|
pending 2nd permit app from applicant
|
1st review completed | | | 12/14/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - Addressing | 12/11/2018 | | 12/12/2018 | | PASS |
Doug Chausow
|
|
|
Suite 150
|
Routing - PUBLIC WORKS | 12/11/2018 | | 12/11/2018 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 12/10/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 7 2018 11:57AM
|
Intake Approval | | | 12/7/2018 | | FAIL |
Michael Hanson
|
|
|
Provide #518 checklist completed and signed
Provide #304 form completed and signed
|