BLD-Final | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | PASS |
Mike Jordan
|
|
|
Please call Dave Phone #: ###-####
|
DOC - Permit Finaled | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | PASS |
Mike Jordan
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/6/2019 | | DONE |
|
|
|
Per Mike J, didn't mean to final permit yet. Another inspection is required.
|
BLD-Final | 1/30/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Mike Jordan
|
|
|
Also refernce tile one letter dated 1-29-19 for complettion of driveway.
|
BLD-Final | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | PEND |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Al isues resolved except for driveway. Will post ond for $1,000 dollars for driveway.
|
BLD-Final | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | FAIL |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Provide code compliant handrail and landings at the bottom of stairs. Will also provide letter from escrow co. showing money has been left in escrow to complete driveway.
|
BLD-Final | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | CANC |
Brandon Shaw
|
|
|
Jeana (homeowner)-foundation final only Phone #: ###-####
|
BLD-Foundation | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Brandon Shaw
|
|
|
Tie downs are in place and attached...
|
BLD-Foundation | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PART |
Mike Jordan
|
|
|
steam wall... late morning // derik Phone #: ###-####
|
BLD-Footing | 12/17/2018 | 12/18/2018 | 12/18/2018 | A | PASS |
Mike Jordan
|
|
|
Derek Phone #: ###-####
|
Plan assigned to (JAB) Josh | 12/17/2018 | 12/17/2018 | 12/17/2018 | | PASS |
Josh Bogle
|
|
|
12/19 foundation, paper
|
Plan assigned to (BJM) | 12/13/2018 | 12/13/2018 | 12/17/2018 | | DEFR |
Brian McGowan
|
|
|
Foundation Only- Paper
|
Routing - PLAN CHECK | 12/14/2018 | | 12/17/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 12/17/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 12/17/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 12/17/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 12/17/2018 | | DONE |
|
|
|
MET
Need
Letter from Parcel owner for Gina to be allowed to pick up permit.
GC Form signed by either Zach or David (parcel owners)
or
parcel owner to pick up permit and fill out GC form
|
Inspection Record Card- Bld | | | 12/17/2018 | | DONE |
|
|
|
|
Telephone call | | | 12/17/2018 | | DONE |
|
|
|
Left voicemail for Gina informing her we need either the parcel owners to write a letter and sign the GC form for her to pick the permit up or the parcel owners to fill out the GC form and pick up the permit. Gave fees due.
|
Issue PAID IN FULL permit | | | 12/17/2018 | | DONE |
|
|
|
|
Routing - Addressing | 12/13/2018 | | 12/14/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | | | 12/14/2018 | | PASS |
|
|
|
|
Route to Impact Fee Review | | 12/18/2018 | 12/13/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 12/13/2018 | | 12/13/2018 | | PASS |
Sue Cummings
|
|
|
See redlines
|
Intake Approval | | | 12/13/2018 | | PASS |
|
|
|
|
Route to Impact Fee Review | 12/10/2018 | 12/13/2018 | 12/11/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Application received | | | 12/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 10 2018 12:21PM
|