FIRE-Final Inspection | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. CO2 detector installed and glycol system installed at 35 gallon max.
Mike Phone #: ###-####
|
BLD-Final | 3/14/2019 | 3/15/2019 | 3/15/2019 | P | PART |
Jim Sly
|
|
|
Mike Phone #: ###-#### OK for Temp. Occ. OK for Perm. Occ. when Fire and Mech. signs off........Perm.
|
FIRE-Final Inspection | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | CANC |
Jim Page
|
|
|
Duplicate inspection request, this request is cancelled.
mike Phone #: ###-####
|
FIRE-Final Inspection | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | PART |
Jim Page
|
|
|
Partial final inspection for life fire safety complete. Glycol system and CO2 have not been installed yet, CO2 will require a detection aoarm due to amount being used. TCO for life fire safety is complete, a follow up inspection will be required after permenant CO2 system and glycol system is installed.
Duplicate inspection request, this request is cancelled.
Mike Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 2/27/2019 | 2/27/2019 | 2/28/2019 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
FIRE-Conference | 2/27/2019 | 2/27/2019 | 2/27/2019 | P | DONE |
Troy Cobbley
|
|
|
Met with Mike discussed requirements needed for final. Mike mentioned not having glycol system installed in time for final so we gave him Ron Johnson's phone and email to discuss possible TCO when they are ready.
Mike Phone #: ###-####
|
Print Occupancy Form | | | 1/30/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/30/2019 | | DONE |
|
|
|
|
Meeting | | | 1/30/2019 | | DONE |
|
|
|
Emailed Mike L, permit to sign.
|
Route to Impact Fee Review | 1/25/2019 | 1/28/2019 | 1/25/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (M_H) | 1/16/2019 | | 1/25/2019 | | DONE |
Michael Hanson
|
|
|
02/12 #520 L3 ePlan. Idaho Kombucha
|
Routing - PLAN CHECK | 1/16/2019 | | 1/25/2019 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 1/25/2019 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 1/25/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/25/2019 | | DONE |
|
|
|
need- met
GC
Rev cert of val
|
Routing - FIRE | 1/16/2019 | 1/16/2019 | 1/24/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLUMBING | 1/16/2019 | | 1/23/2019 | | PASS |
Dan Ediger
|
|
|
Eyewash deleted per the engineer Steve Trout. Per ISPC and approved plans
|
Routing PW Environmental | 1/17/2019 | | 1/22/2019 | | PASS |
Terry Alber
|
|
|
No Pretreatment issues.
|
Routing - Addressing | 1/16/2019 | | 1/17/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/16/2019 | | 1/17/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - MECHANICAL | 1/16/2019 | | 1/17/2019 | | PASS |
Troy James
|
|
|
On demand water heater only shown on plans. Field verify venting and gas piping.
|
Routing - Design Review | 1/16/2019 | | 1/17/2019 | | PASS |
Katelyn Menuge
|
|
|
CZC18-00269
|
Intake Approval | | | 1/11/2019 | | PASS |
|
|
|
|
Intake Approval | | | 12/24/2018 | | FAIL |
Brian McGowan
|
|
|
Please resolve the following corrections for the Prescreen to be approved.
1. Provide Information and Installation details on the cooler, Kettle, Brite Tanks and Fermenter Tanks.
2. Show any exit signs and emergency lighting required on the plans.
3. A Mechanical Plan may be required depending on the installation requirements of the proposed equipment to be installed.
4. Does the addition of the cooler and other equipment trigger the need for a Lighting Plan, COMchecks, heating and cooling calculations? Please verify and resubmit any relevant information.
|
Intake Approval | | | 12/17/2018 | | FAIL |
Brian McGowan
|
|
|
Please resolve the following corrections for the Prescreen to be approved.
1. Complete the Table of Contents on Sheet A1.0
2. Provide an Existing Floor Plan (as is drawing).
3. Provide Information and Installation details on the cooler, Kettle, Brite Tanks and Fermenter Tanks.
4. Show any exit signs and emergency lighting required on the plans.
5. A Mechanical Plan may be required depending on the installation requirements of the proposed equipment to be installed.
6. Does the addition of the cooler and other equipment trigger the need for a Lighting Plan, COMchecks, heating and cooling calculations? Please verify and resubmit any relevant information.
|
Application received | | | 12/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 12 2018 9:19AM
|