BLD-Final | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Dave Hannah
|
|
|
|
Print Occupancy Form | | | 4/17/2020 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/18/2019 | 4/19/2019 | 4/19/2019 | P | PASS |
Jim Sly
|
|
|
Dusty Phone #: ###-#### Frame and Energy....OK Insulated areas exposed by remodel. Performance Engineering approved adding 2x6 fir at areas below HVAC......Done.
|
Routing - MECHANICAL | 4/19/2019 | | 4/19/2019 | | PASS |
Troy James
|
|
|
Manual j report
|
BLD-Conference | 3/19/2019 | 3/20/2019 | 3/20/2019 | A | PART |
Tony Young
|
|
|
Please call Dusty for access Phone #: ###-####,, job walk through,, recomend having structural engineer do an on-site walk through now that it is opened up to address roof loads
|
Routing Walk-In (BLD) | 1/23/2019 | 1/23/2019 | 1/23/2019 | A | DONE |
Josh Bogle
|
|
|
Call Kaycee 7080. possibly will have an appeal period (DRH19-00023)
|
Routing Walk-In (Zoning) | 1/23/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Katelyn Menuge
|
|
|
Applicant can proceed with building permit at own risk- 10 day appeal period is still in effect.
|
Routing - PLAN CHECK | 1/23/2019 | | 1/23/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 1/23/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 1/23/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/23/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 1/23/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/23/2019 | | DONE |
|
|
|
per walk in zoning activity KBM states we can proceed with the building permit at own risk.
|
Plan Reviewer's activity | | | 1/14/2019 | | DONE |
Josh Bogle
|
|
|
called Dusty asking for egress window information
|
Routing Walk-In (BLD) | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | FAIL |
Josh Bogle
|
|
|
Needs compliant stair details
|
Routing Walk-In (BLD) | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | FAIL |
Josh Bogle
|
|
|
needs Historic approval first
|
Meeting | | | 12/12/2018 | | DONE |
|
|
|
as per Ted V-no DR required-going over the stucco is considered repairs to the cracking-color is going to be white to light cream
|
1st review completed | | | 12/12/2018 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 12/12/2018 | | | |
|
|
|
|