BLD-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | PASS |
Brandon Shaw
|
|
|
Todd Phone #: ###-####
|
DOC - Permit Finaled | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/29/2019 | 5/29/2019 | 5/29/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.6
|
BLD-Energy code compliance | 3/26/2019 | 3/27/2019 | 3/27/2019 | P | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### verafy attic r value to plan at final.ok to cover.
|
BLD-Framing/Rough-in | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### c/n made ok
|
BLD-Framing/Rough-in | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | FAIL |
Jim Storey
|
|
|
Bobby Phone #: ###-#### ijoist top chord cut at tub/side nail hangers mlb at stairs/ eo1 bottom bearing/ ao4 bearing center not per engineering.
|
BLD-Other | 3/12/2019 | 3/13/2019 | 3/13/2019 | A | PASS |
Jim Storey
|
|
|
sofit // Bobby Phone #: ###-####
|
BLD-Wall Bracing | 3/4/2019 | 3/4/2019 | 3/4/2019 | P | PASS |
Jim Storey
|
|
|
Bobbi Phone #: ###-####
|
BLD-Footing | 1/16/2019 | 1/17/2019 | 1/17/2019 | A | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/15/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/15/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/2/2019 | | |
|
|
|
|
Routing - PLAN CHECK | 1/2/2019 | | 1/2/2019 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/2/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/2/2019 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 12/18/2018 | | 1/2/2019 | | DONE |
Michael Hanson
|
|
|
12/31 #402 L1 ePlan. 1st review completed - See changemarks in ePlan for corrections required.
|
Routing - PLAN CHECK | 12/18/2018 | | 12/28/2018 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
1st review completed | | | 12/28/2018 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
Routing - MECHANICAL | 12/18/2018 | | 12/20/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 12/18/2018 | 12/21/2018 | 12/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 12/18/2018 | | 12/19/2018 | | PASS |
Laura Hunter
|
|
|
|
Routing - PLANNING | 12/18/2018 | | 12/18/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 12/18/2018 | | 12/18/2018 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 12/18/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/18/2018 | | DONE |
|
|
|
|
Application received | | | 12/14/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 14 2018 3:09PM
|