BLD-Final | 7/30/2019 | 7/31/2019 | 7/31/2019 | A | PASS |
Brandon Shaw
|
|
|
Les Phone #: ###-####
|
DOC - Permit Finaled | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/31/2019 | 7/31/2019 | 7/31/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.9
|
PubWorks Occupancy Approval | 7/31/2019 | 7/31/2019 | 7/31/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 7/30/2019 | 7/30/2019 | 7/30/2019 | P | CANC |
Brandon Shaw
|
|
|
Less Phone #: ###-####
|
BLD-Final | 7/29/2019 | 7/30/2019 | 7/30/2019 | A | CANC |
Brandon Shaw
|
|
|
Les Phone #: ###-####
|
BLD-Energy code compliance | 4/16/2019 | 4/17/2019 | 4/17/2019 | A | PASS |
Brandon Shaw
|
|
|
les Phone #: ###-####
|
BLD-Other | 4/15/2019 | 4/15/2019 | 4/15/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Framing/Rough-in | 4/15/2019 | 4/15/2019 | 4/15/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Framing/Rough-in | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | NR |
Brandon Shaw
|
|
|
Need Fire rough-in...
|
BLD-Wall Bracing | 3/22/2019 | 3/22/2019 | 3/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 2/5/2019 | 2/6/2019 | 2/6/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
BLD-Footing | 1/31/2019 | 1/31/2019 | 1/31/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
PubWorks Subgrade Approval | 1/29/2019 | 1/29/2019 | 1/29/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Telephone call | | | 1/18/2019 | | DONE |
|
|
|
Emailed applicant/gc to inform them not all the fees have been paid and once the remaining fees are paid we can then issue the permits.
|
Issue PAID IN FULL permit | | | 1/18/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/18/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/7/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 12/17/2018 | 12/17/2018 | 1/7/2019 | | DONE |
Brian McGowan
|
|
|
01/07 sfd L2 ePlan
|
Routing - PLAN CHECK | 12/17/2018 | | 1/7/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 1/7/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 1/7/2019 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 12/17/2018 | | 12/20/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Route to Impact Fee Review | 12/17/2018 | 12/20/2018 | 12/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 12/17/2018 | | 12/18/2018 | | PASS |
Laura Hunter
|
|
|
|
Routing - FIRE | 12/17/2018 | 12/17/2018 | 12/17/2018 | | PASS |
Lee G Meredith
|
|
|
An NFPA 13D fire sprinkler system is to be provided, as noted on the drawings.
|
Routing - Erosion and Sediment | 12/17/2018 | | 12/17/2018 | | PASS |
Michael Zawacki
|
|
|
|
Routing - PUBLIC WORKS | 12/17/2018 | | 12/17/2018 | | PASS |
Angela Hardy
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/17/2018 | | DONE |
|
|
|
|
Routing - MECHANICAL | 12/17/2018 | | 12/17/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/17/2018 | | 12/17/2018 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 12/14/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 14 2018 4:18PM
|