BLD-Final | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Band
|
Letter of compliance/Occupancy | | | 10/21/2019 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 10/21/2019 | | DONE |
|
|
|
Per passing BLD Final from 425 on 10/21/19
|
BLD-Final | 10/17/2019 | 10/17/2019 | 10/17/2019 | A | PART |
Mike Jordan
|
|
|
Needs to repair and provide an additional handrail on the ramp on the north west side of building. his ramp is not part of the accesible route or egress.
|
BLD-Final | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | NR |
Mike Jordan
|
|
|
T.I. contractor was told we needed a structural inspection w/ Dave Hannah We had a framing Inspection for shell in June or July, w/ Mike Jordan Phone #: ###-#### Inspection requested via web by Gary Band. Noted that zoning final failed back in July. Needs to resolve and get reinspection.
|
BLD-Conference | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | DONE |
Mike Jordan
|
|
|
T.I. contractor was told we needed a structural inspection w/ Dave Hannah We had a framing Inspection for shell in June or July, w/ Mike Jordan ??? Phone #: ###-#### Inspection requested via web by Gary Band
|
Zoning Approval | 10/17/2019 | 10/17/2019 | 10/17/2019 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm permit under tenant improvement permit, fire extinguishers provided by tenant improvement. Final life fire safety inspection for this scope of work complete.
Looking for Life, Fire, Safety Inspection so T.I. contractor can get his final. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Wall cover | 7/26/2019 | 7/29/2019 | 7/30/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Band covering int side of ext walls for shell and core
|
Zoning Approval | 7/29/2019 | 7/29/2019 | 7/29/2019 | | FAIL |
Katelyn Menuge
|
|
|
Metal Panel not installed on building exterior- need to install or bond.
|
BLD-Framing/Rough-in | 7/13/2019 | 7/15/2019 | 7/15/2019 | A | PASS |
Dave Hannah
|
|
|
request is for a framing inspection of exterior soffit steel framing under the canopies. F/S ; elect inspections have been completed. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Wall cover | 6/28/2019 | 6/28/2019 | 6/28/2019 | A | CANC |
Mike Jordan
|
|
|
looking for insulation inspection - by offered listings, not sure if it''s this or "energy compliance" Thank you Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Energy code compliance | 6/28/2019 | 6/28/2019 | 6/28/2019 | A | PASS |
Mike Jordan
|
|
|
looking for insulation inspection - by offered listings, not sure if it''s this or "wall cover" Thank you Phone #: ###-#### Inspection requested via web by Gary Band
|
FIRE-Conference | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | CANC |
Jim Page
|
|
|
|
FIRE-Conference | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | DONE |
Jim Page
|
|
|
Gas meter is set in the wrong location, city approved drawings show gas meter by north door, currently meter is set under PIV for fire sprinklers, needs to be relocated to give the required 36 inch clearance around PIV.
|
BLD-Framing/Rough-in | 6/25/2019 | 6/26/2019 | 6/26/2019 | P | DONE |
Mike Jordan
|
|
|
Request for shell framing inspection - Phone #: ###-#### Inspection requested via web by Gary Band. Completed in the am.
|
BLD-Framing/Rough-in | 6/25/2019 | 6/26/2019 | 6/26/2019 | A | PASS |
Mike Jordan
|
|
|
Request for shell framing inspection - Phone #: ###-#### Inspection requested via web by Gary Band. Ok to insulate.
|
BLD-Wall Bracing | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Dave Hannah
|
|
|
request shear and roof nailing inspection Tuesday morning. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Foundation | 3/29/2019 | 4/2/2019 | 4/2/2019 | A | PASS |
Dave Hannah
|
|
|
stem wall forms / rebar inspection request MTI will also look at bar w/ concrete testing request late morning for 2:00 pm pour Best access @ E gate into project from W edge of parking lot Thank you. Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Foundation | 3/29/2019 | 4/2/2019 | 4/2/2019 | P | CANC |
Dave Hannah
|
|
|
stem wall forms / rebar inspection request MTI will also look at bar w/ concrete testing request early afternoon insp for 2:00 pm pour Best access @ E gate into project from W edge of parking lot Thank you. Phone #: ###-#### >> Inspection requested via web by Gary Band Inspection cancelled from web by: Gary Band
|
BLD-Footing | 3/26/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Dave Hannah
|
|
|
Request footing inspection early afternoon for 2;00 pm pour. Corner of Capitol ; Broad. 390 S Capitol Blvd. just S of Trader Joes. Best access @ East site gate off W edge of TJ''s parking lot. Can temp park in gate opening. Thank you! Phone #: ###-#### Inspection requested via web by Gary Band
|
BLD-Footing | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PEND |
Dave Hannah
|
|
|
Request footing inspection late morning for 2;00 pm pour. Corner of Capitol ; Broad. 390 S Capitol Blvd. just S of Trader Joes. Best access @ East site gate off W edge of TJ''s parking lot. Can temp park in gate opening. Thank you! Phone #: ###-#### Inspection requested via web by Gary Band ok after spec inspection is aproved
|
Issue PAID IN FULL permit | | | 2/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/19/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 2/14/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 12/20/2018 | 12/27/2018 | 2/14/2019 | | DONE |
Julie Romig
|
|
|
02/14 - 1st Rev Comp - 2nd Rev - 502 Capitol & Front Pad 3 Shell
|
Routing Off Site - STRUCTURAL | 2/7/2019 | | 2/14/2019 | | PASS |
Julie Romig
|
|
|
AHJ - 2nd Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/14/2019 | | DONE |
|
|
|
Need the following:
Revised Value (need second page of form)
all met-
RP
GC Form
|
Routing - FIRE | 2/7/2019 | 2/7/2019 | 2/8/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Fire Review 02082019.pdf.
|
Routing - PLAN CHECK | 2/7/2019 | | 2/8/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - Design Review | 2/7/2019 | | 2/7/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 1/29/2019 | 2/1/2019 | 1/31/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/29/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 12/27/2018 | | 1/29/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 12/20/2018 | 12/27/2018 | 1/25/2019 | | FAIL |
Mark Scharfen
|
|
|
1/25/2019 Fire code review uploaded and emailed architect.
|
Routing Off Site - STRUCTURAL | 12/27/2018 | | 1/11/2019 | | FAIL |
Julie Romig
|
|
|
AHJ
|
Routing PW Environmental | 12/28/2018 | | 1/11/2019 | | PASS |
Terry Alber
|
|
|
Grease interceptor shown OK.
|
Routing PW Street Lights | 12/28/2018 | | 1/3/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 12/28/2018 | | 1/2/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 12/28/2018 | | 12/31/2018 | | PASS |
Brian Murphy
|
|
|
APPROVED AS PART OF MASTER PLAN PAD EXISTING SYSTEM
|
Routing - PLANNING | 12/27/2018 | | 12/31/2018 | | PASS |
Katelyn Menuge
|
|
|
See Design Review
|
Routing - Design Review | 12/27/2018 | | 12/31/2018 | | FAIL |
Katelyn Menuge
|
|
|
Lighting was not approved through the design review. Need to remove from permit.
|
Routing - PUBLIC WORKS | 12/27/2018 | | 12/28/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Sewer Design | 12/28/2018 | | 12/28/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Erosion and Sediment | 12/27/2018 | | 12/27/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed before work begins.
Site prep inspection required.
|
Routing - Addressing | 12/27/2018 | | 12/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 12/27/2018 | | 12/27/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 12/27/2018 | | 12/27/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 12/20/2018 | | PASS |
Julie Romig
|
|
|
Prescreen approved by JAR
|
Application received | | | 12/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 17 2018 9:58AM
|