BLD-Aging Inspection | 7/18/2019 | 7/18/2019 | 7/26/2019 | | PEND |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 3/5/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection for area of work complete.
|
FIRE-Final Inspection | 3/4/2019 | 3/4/2019 | 3/4/2019 | P | FAIL |
Jim Page
|
|
|
Could not locate city approved draiwngs for work that was completed.
Dave Phone #: ###-####
|
BLD-Final | 2/27/2019 | 2/28/2019 | 3/1/2019 | P | NR |
Jim Sly
|
|
|
Dave Phone #: ###-#### Called Dave.......Need Fire / Life safety inspection.
|
BLD-Framing/Rough-in | 1/28/2019 | 1/28/2019 | 1/28/2019 | A | PASS |
Dave Hannah
|
|
|
Dave Phone #: ###-#### hard ceiling
|
BLD-Conference | 1/25/2019 | 1/25/2019 | 1/28/2019 | P | DONE |
Dave Hannah
|
|
|
Dave Phone #: ###-####
|
Inspection Record Card- Bld | | | 1/17/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/17/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/20/2018 | 12/20/2018 | 1/15/2019 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/24 L1 Hal Davis Jewlers ePlan
|
Routing - PLAN CHECK | 1/9/2019 | | 1/15/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/15/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/15/2019 | | DONE |
|
|
|
NEED
GC
Rev cert of val
|
Route to Impact Fee Review | 12/24/2018 | 12/27/2018 | 12/26/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/20/2018 | | 12/24/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 12/20/2018 | | 12/24/2018 | | PASS |
Doug Chausow
|
|
|
|
1st review completed | | | 12/24/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 12/20/2018 | | 12/20/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 12/19/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 17 2018 11:03AM
|