DOC - Permit Finaled | | | 5/20/2019 | | |
|
|
|
pass final
|
Letter of compliance/Occupancy | | | 5/20/2019 | | |
|
|
|
|
BLD-Final | 5/16/2019 | 5/17/2019 | 5/17/2019 | A | DONE |
Dave Hannah
|
|
|
Larren Phone #: ###-####
|
BLD-Final | 5/16/2019 | 5/16/2019 | 5/17/2019 | P | PASS |
Dave Hannah
|
|
|
Larren Phone #: ###-####
|
FIRE-Final Inspection | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for area of work complete.
|
Issue PAID IN FULL permit | | | 1/14/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/14/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/19/2018 | 12/19/2018 | 1/8/2019 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/31 L2 Vanilla ePlan under BLD18-04315
|
Routing - PLAN CHECK | 1/7/2019 | | 1/8/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/8/2019 | | DONE |
|
|
|
MET
Need
GC Form
Revised Value (for each suite)
DO NOT ISSUE WITHOUT BLD18-04315
|
Routing - MECHANICAL | 1/8/2019 | | 1/8/2019 | | PASS |
Troy James
|
|
|
Vanilla shell
|
Routing - PLAN CHECK | 1/4/2019 | | 1/4/2019 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 12/31/2018 | 1/3/2019 | 1/2/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 12/31/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 12/19/2018 | | 12/31/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 12/19/2018 | | 12/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/19/2018 | | 12/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 12/19/2018 | | 12/19/2018 | | PASS |
Daryl Spivey
|
|
|
Passed in bld18-04315
|
Intake Approval | | | 12/19/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2018 1:49PM
|