First Notice | | 7/25/2019 | 8/13/2019 | | DONE |
|
|
|
mailed 8-14-19
|
Permanent Occupancy | | | 7/15/2019 | | DONE |
|
|
|
|
BLD-Final | 7/10/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Dave Hannah
|
|
|
Please call 30min ahead to allow time to meet you. Thanks Phone #: ###-#### Inspection requested via web by Ron Douthit
|
FIRE-Final Inspection | 7/8/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags, knox box is located by west exit, this door is fire riser access. Final life fire safety inspection complete.
We would like Life Safety paired with he alarm final Thursday. Thanks. RON Phone #: ###-#### Inspection requested via web by Ron Douthit
|
Zoning Approval | 7/11/2019 | 7/11/2019 | 7/11/2019 | | DONE |
Jeff Lowe
|
|
|
|
FIRE-Final Inspection | 7/2/2019 | 7/3/2019 | 7/3/2019 | A | FAIL |
Jim Page
|
|
|
Need FIR permits for fire sprinkler and fire alarm finaled before life fire safety inspection can be performed.
Ron Phone #: ###-####
|
BLD-Framing/Rough-in | 4/30/2019 | 5/1/2019 | 5/1/2019 | A | PASS |
Dave Hannah
|
|
|
Re inspection for sealing around plumbing pipes Phone #: ###-#### Inspection requested via web by Ron Douthit
|
BLD-Framing/Rough-in | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ron Douthit walls ok but need to foam holes in floor
|
Place hold on job | 3/28/2019 | | 4/1/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
waiting for signed permit
|
Telephone call | | | 4/1/2019 | | DONE |
|
|
|
emailed GC a reminder to print and sign on building permit and email it back.
|
Print Occupancy Form | | | 3/28/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/28/2019 | | DONE |
|
|
|
|
Telephone call | | | 3/26/2019 | | DONE |
|
|
|
emailed them informing them that the RCE number they included on the GC form they emailed to permits on 3-26-2019 is invalid. Requested a valid RCE number
|
Plan assigned to (JHB) | 2/14/2019 | 2/14/2019 | 3/25/2019 | | PASS |
Joe Bruce
|
|
|
03/22 (1st Resub) 03/14 (L3) Revolution 22 (Bldg, Mech, Plumb, Fire, Struc, DR)
|
Routing Off Site - STRUCTURAL | 3/18/2019 | | 3/25/2019 | | PASS |
Joe Bruce
|
|
|
AHJ
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/25/2019 | | DONE |
|
|
|
NEED=all met
ACHD-met
GC FORM
REVISED VALUE - met
|
Routing - FIRE | 3/18/2019 | 3/18/2019 | 3/22/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Final review 03.22.2019.pdf uploaded.
|
Routing - Design Review | 3/18/2019 | | 3/21/2019 | | PASS |
KayCee Babb
|
|
|
Per CZC19-00012. No exterior alterations beyond rooftop mechanical equipment and parking approved through this permit.
|
Routing - PLAN CHECK | 3/18/2019 | | 3/20/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing - MECHANICAL | 3/18/2019 | | 3/18/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/18/2019 | | 3/18/2019 | | PASS |
Daryl Spivey
|
|
|
Per ISPC 407.3 install tempering device on lavs as required.
|
Plan resubmittals received | | | 3/18/2019 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 3/14/2019 | 3/17/2019 | 3/15/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/14/2019 | 2/14/2019 | 3/14/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 03.14.2019.pdf uploaded and emailed to architect.
|
1st review completed | | | 3/14/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 3/14/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 2/14/2019 | | 3/14/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 2/14/2019 | | 2/28/2019 | | FAIL |
Joe Bruce
|
|
|
AHJ - Corrections Required.
|
Routing - MECHANICAL | 2/14/2019 | | 2/21/2019 | | FAIL |
Troy James
|
|
|
See eplan for corrections
|
Routing - PLANNING | 2/14/2019 | | 2/15/2019 | | PASS |
Jeff Lowe
|
|
|
Per CZC19-00012.
|
Routing - Addressing | 2/14/2019 | | 2/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Design Review | 2/15/2019 | | 2/15/2019 | | PASS |
KayCee Babb
|
|
|
Per CZC19-00012. Change of Use Zoning Certificate to stand in for Design Review. ADA parking stall alterations and mechanical units are approved. Any other exterior alterations shall require additional review.
|
Routing - PUBLIC WORKS | 2/14/2019 | | 2/14/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 2/14/2019 | | 2/14/2019 | | FAIL |
KayCee Babb
|
|
|
A Zoning Certificate is required for all exterior alterations, including rooftop mechanical equipment and new parking lot layout. Additionally, site requires a parking reduction or permanent parking agreement for use/proposed seating. A temporary parking lease is not sufficient. If you have any questions, you can reach KayCee Babb at ###-####.
|
Routing - PLUMBING | 2/14/2019 | | 2/14/2019 | | FAIL |
Daryl Spivey
|
|
|
Need service protection on water and increase cold water pipe sizing to 1 1/2 in for upstairs plumbing.
|
Intake Approval | | | 2/14/2019 | | PASS |
|
|
|
|
Intake Approval | | | 2/5/2019 | | FAIL |
Joe Bruce
|
|
|
5) Provide shared access and parking agreement with legal description of shared property that is signed and notarized. Upload this document into the "documents" folder.
6) Provide design review approval for new mechanical unit RTU-4 located on rooftop. Contact: Kaycee Babb - ###-####
9) Provide structural plans for the modification to the floor / roof framing and rooftop unit. Plans must be stamped by a structural engineer.
|
Intake Approval | | | 12/26/2018 | | FAIL |
Joe Bruce
|
|
|
1) Form #304 needs to be completely filled out with design professional and owner information.
2) Structural calculations must have the engineers stamp on the cover page with signature and date.
3) Last page of structural calculations states "NOT FOR PERMIT." This is required to be removed and affixed with the structural engineers stamp and signature.
4) Provide site specific flow at hydrants letter from Suez water for this address.
5) Provide shared access and parking agreement with legal description of shared property that is signed and notarized. Upload this document into the "documents" folder.
6) Provide design review approval for new mechanical unit RTU-4 located on rooftop. Contact: Kaycee Babb - ###-####
7) Show portable fire extinguishers on plan. Sheet G-002 makes mention in the notes, but does not locate them on the plan.
8) Exit signs could not be located on the lower level lighting plan. Locate all exit signs including new and existing.
9) Provide structural plans for the modification to the floor framing. Plans must be stamped by a structural engineer.
|
Application received | | | 12/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 20 2018 2:51PM
|