BLD-Final | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Brandon Shaw
|
|
|
Greg-please call prior for access Phone #: ###-####
|
DOC - Permit Finaled | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.6
|
BLD-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | FAIL |
Mike Jordan
|
|
|
Greg-call for access Phone #: ###-####. Provide the blower door test results and post. Complete grading. Need to provide min. 2% slope from foundation. Correction notice posted.
|
BLD-Energy code compliance | 3/29/2019 | 4/1/2019 | 4/1/2019 | A | PASS |
Mike Jordan
|
|
|
Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Wall Bracing | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Brandon Shaw
|
|
|
Greg Phone #: ###-####
|
BLD-Wall Bracing | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | NR |
Mike Jordan
|
|
|
Louis Phone #: ###-####
|
BLD-Wall Bracing | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | PART |
Mike Jordan
|
|
|
possible first thing in the amLuis Phone #: ###-####. portal frame construction only at front of house. Tyvek install ok. Will needs another inspection when the T11 structural siding has been installed. will alos need the ICC ESR report on site as well.
|
BLD-Foundation | 2/4/2019 | 2/4/2019 | 2/4/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constr
|
BLD-Foundation | 1/30/2019 | 1/31/2019 | 1/31/2019 | P | PEND |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron lira. Need 7 day break results prior to concrete placement.
|
BLD-Conference | 1/30/2019 | 1/31/2019 | 1/30/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron lira Inspection cancelled via mobile web on Wednesday, January 30, 2019.
|
BLD-Foundation | 1/29/2019 | 1/30/2019 | 1/30/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | FAIL |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate construction. Onsite. stemwall not yet constructed. Footing concrete was placed yesterday. Noted no concrete blankets on site and conc. footings were not covered. Called Ricardo with aggerate construction and requested core samples from footing for strenght test. Noted stemwall will not be allowed to be placed until 7 day strength test results are given.
|
BLD-Footing | 1/23/2019 | 1/24/2019 | 1/24/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
Issue PAID IN FULL permit | | | 1/16/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/15/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 12/27/2018 | 12/27/2018 | 1/15/2019 | | DONE |
Jenny Nelson
|
|
|
01/3 sfd L1 paper. 1st complete 12/31, Failed planning, needs engineered foundation for hillside home, site plan to scale, update wall bracing calcs to wind speed 115 mph
|
Inspection Record Card- Bld | | | 1/15/2019 | | DONE |
|
|
|
|
Telephone call | | | 1/15/2019 | | DONE |
|
|
|
Spoke with Tim to inform him the permit is ready and what fees are due.
|
Permit Ready to Issue | | | 1/15/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/14/2019 | | DONE |
|
|
|
Resibmittal received 4 copies of the site plan-2 big-2 small-took to Jenny
|
Routing - Addressing | 1/14/2019 | | 1/14/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLAN CHECK | 1/11/2019 | | 1/11/2019 | | PASS |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 1/11/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 1/10/2019 | | 1/10/2019 | | PASS |
Sue Cummings
|
|
|
Unidentified pipe in rear yard...no easement noted on plat, or the two ROSs 10621 or 10791
|
Plan resubmittals received | | | 1/10/2019 | | DONE |
|
|
|
two copies of sheet S1. taken to Jenny
|
Plan resubmittals received | | | 1/9/2019 | | DONE |
|
|
|
resubmittals received 2 large and 2 small sheets site plan-took to Jenny
|
1st review completed | | | 12/31/2018 | | FAIL |
Jenny Nelson
|
|
|
Failed planning, needs engineered foundation for hillside home, site plan to scale, update wall bracing calcs to wind speed 115 mph
|
Routing - PLAN CHECK | 12/27/2018 | | 12/31/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 12/27/2018 | 12/30/2018 | 12/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Meeting | | | 12/27/2018 | | DONE |
|
|
|
Jenny came up about intake approved, recd pcfee&taken to and plans accepted by; tasks were not added by tech who did second review and wanted to make sure plans were good to go. Added in the three task to show that they had be taken in and routing started
|
Routing - MECHANICAL | 12/26/2018 | | 12/27/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/26/2018 | | 12/26/2018 | | FAIL |
Sue Cummings
|
|
|
Site plan not to scale. Please identify line through the rear yard
|
Routing - Addressing | 12/24/2018 | | 12/24/2018 | | FAIL |
Doug Chausow
|
|
|
Address and/or Lot and Block number needs to be put on plans.
|
Routing - PUBLIC WORKS | 12/24/2018 | | 12/24/2018 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 12/21/2018 | | FAIL |
|
|
|
Missing Site Plan on the actual plans.
Need a letter from Hayden Homes allowing Simplicity Homes to use their plans.
|
Intake Approval | | | 12/21/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 12/21/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/21/2018 | | DONE |
|
|
|
|
Application received | | 12/21/2018 | | | |
|
|
|
|