Letter of compliance/Occupancy | | | 5/31/2019 | | DONE |
|
|
|
|
BLD-Final | 5/22/2019 | 5/23/2019 | 5/23/2019 | A | PASS |
Jim Sly
|
|
|
Garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle Blower Door.....3.89
|
DOC - Permit Finaled | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 4/3/2019 | 4/8/2019 | 4/8/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Foundation | 3/11/2019 | 3/12/2019 | 3/12/2019 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 3/8/2019 | 3/11/2019 | 3/11/2019 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/19/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/30/2019 | | |
|
|
|
|
Routing - PLAN CHECK | 1/30/2019 | | 1/30/2019 | | PASS |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 1/30/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/30/2019 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 1/9/2019 | | 1/30/2019 | | DONE |
Michael Hanson
|
|
|
01/22 #402 L1 ePlan. 1st review completed - See changemarks for corrections required. MDH
|
Routing - PLAN CHECK | 1/9/2019 | | 1/22/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks for corrections required. MDH
|
Routing - PLANNING | 1/9/2019 | | 1/22/2019 | | PASS |
Sue Cummings
|
|
|
Per ePlan approval.
|
1st review completed | | | 1/22/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks for corrections required. MDH
|
Routing - MECHANICAL | 1/9/2019 | | 1/11/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 1/9/2019 | 1/12/2019 | 1/10/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 1/9/2019 | | 1/10/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/9/2019 | | 1/9/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/9/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2019 | | DONE |
|
|
|
|
Application received | | | 12/28/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 28 2018 10:32AM
|
Telephone call | | | 12/28/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
Spoke with Gloria to inform her that a building permit has already been applied for on this address (see BLD18-03620). She informed me that she will check with her boss and call back on Monday 12/31/18.
Need to know if we are going to void this permit or change the address.
|