Permit Information
Permit NumberBLD18-04579
StatusFinaled
Name EKC INC
Site Address 1509 N 13TH ST
Project Name1509 N. 13th St. Shell & Core
Customer Number 
ePlanReviewYes
Description
(SHELL AND CORE – HYDE PARK – TWO TENANT IMPROVEMENT PERMITS TO FOLLOW) (DRH18-00519) (CUP18-00101) (5-22-19 PLAN MODIFICATION TO EVALUATE THE PARTY WALLS LOCATED ON PROPERTY LINES AS FIRE WALLS WITHOUT OPENINGS INSTEAD OF BEING EVALUATED AS PROPERTY LINE WALLS. ALL PARAPETS ON PARTY WALLS HAVE BEEN DELETED. EACH 2-HR PARTY WALL IS ALLOWED TO TERMINATE AT THE UNDERSIDE OF THE ROOF DECK. THE CEILINGS LOCATED NEXT TO THE PARTY WALLS ON EACH SIDE AND THEIR SUPPORTING CONSTRUCTION ARE REQUIRED TO HAVE A MINIMUM 1-HR FIRE-RESISTANCE-RATING, NO OPENINGS . . .) (3-12-19 PLAN MODIFICATION TO REVISE THE DRAWINGS: (1) TO REFLECT EXISTING STRUCTURAL CONDITIONS, TO MODIFY THE ROOF FRAMING PLAN, TO INCREASE THE SIZE OF CONCRETE FOOTINGS, TO RELOCATE OR REORIENT ROOF TOP HVAC UNITS, TO CREATE ROOF OPENINGS FOR HVAC DUCTS, TO SHOW FUTURE ROOF TOP EQUIPMENT TO SERVE A FUTURE KITCHEN, TO EXTEND 2-HR PARAPETS ON PROPERTY LINE WALLS, AND TO CREATE A ROOF OPENING FOR A NEW SKYLIGHT; (2) TO DO ADDITIONAL MECHANICAL, PLUMBING, AND ELECTRICAL WORK FOR THE FUTURE SOUTH TENANT SPACE; AND (3) TO MODIFY THE WATER METER AND SERVICE LOCATION DUE TO EXISTING CONDITIONS. ACCORDING TO THE REVISED CERTIFICATE OF VALUE, THE VALUE OF THE WORK IS INCREASING BY $40,000. THE AVERAGE POWER USED FOR LIGHTING IN THE SOUTH TENANT SPACE WILL BE ABOUT .42 WATTS PER SQUARE FOOT. THIS PERMIT IS NOT INTENDED TO ESTABLISH A CERTIFICATE OF OCCUPANCY FOR ANY TENANT. SEPARATE TENANT IMPROVEMENT PERMITS ARE REQUIRED TO ESTABLISH OCCUPANCY.) This building does not have a fire sprinkler system. To avoid a fire sprinkler system, the fire area that will contain a future A-2 Occupancy is limited to 99 occupants. Interior nonstructural demolition work was done under permit BLD19-00126. To perform shell and core work to an existing 4,067 square foot building in preparation for two future tenants (about 2,022 square feet and about 1,946 square feet) that will each apply for their own tenant improvement permit. One tenant is expected to be a bar and one tenant is expected to be a restaurant/bakery. Work is to include constructing the 2nd half of a 2-hr party wall at the North property line from the top of an existing masonry wall to the roof deck (the 1st half was constructed under permit BLD15-03600) and constructing a 2-hr parapet on top of that wall, upgrading an existing interior wall to comply as a 2-hr fire barrier wall to create separate fire areas, a 1-hr ceiling membrane throughout the building in lieu of a parapet on a portion of the party wall at the North property line and in lieu of a parapet on the party wall at the South property line, new concrete floor slabs on grade, a recessed alcove for an exit door at the alley, new glass high-lift overhead door, new store front door, new windows, 4 toilet rooms accessible to the disabled, new roof membrane above R-30 continuous insulation installed on top of the roof deck (existing removed down to the roof deck), 342 square foot exterior concrete patio, wood and chain link trash enclosure, new skylights on existing curbs, and changing existing doors to be outswing doors at the public way with substantial planters to direct the passing public away from the doors. Structural work includes concrete footings, new masonry wall infills, steel moment frames with steel columns and steel beams, new roof joists to support new roof top HVAC units, new roof joists to replace failing or damaged roof joists, new roof beams, ties between a portion of the roof diaphragm and reconstructed exterior walls, and a steel header and jambs at a new opening in an exterior masonry wall. Special Inspection is required for soils, concrete, masonry, structural steel (including welding and bolting), and for post-installed anchors in hardened concrete (including epoxy anchors and Titan anchors). The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/12/20199/12/20199/12/2019PPASS
DetailsDave Hannah
FIRE-Final Inspection9/4/20199/4/20199/4/2019PPASS
DetailsJim Page
Final life fire safety inspection for area of work complete, signature card not available for signature.

dALE Phone #: ###-####
Zoning Approval6/19/20196/19/20196/19/2019 DONE
DetailsTed Vanegas
FIRE-Final Inspection6/18/20196/18/20196/18/2019PPART
DetailsJim Page
No fire sprinkler, no fire alarms, fire extinguishers in the 1509 addressed area are placed with current inspection tags. Partial final for life fire safety inspection complete for the 1509 address side of the core and shell project, restrooms on the 1511 address side are part of the core and shell remodel, restrooms on mentioned side will still need to be completed for core and shell sign off for life fire safety. Per conversation with Ron Johnson with Boise Fire a 90 day TCO is authorized contingent on the restrooms being completed on the 1511 address side.



Dale Phone #: ###-####
BLD-Framing/Rough-in6/17/20196/17/20196/17/2019PPART
DetailsTony Young
Dale Phone #: ###-####// 2 hour firewall on north side,, beam/post connections
BLD-Final6/5/20196/6/20196/6/2019ANR
DetailsTony Young
DALE Phone #: ###-####
BLD-Framing/Rough-in6/5/20196/6/20196/6/2019APART
DetailsTony Young
DALE Phone #: ###-####,, roof area on north unit ok
CHANGE STATUS TO (ISS)  5/28/2019 DONE
OVERRIDE  5/22/2019  
Plan assigned to (CJW)5/17/20195/17/20195/22/2019 PASS
DetailsCarl Westfall
Plan mod - Hyde Park shell and core (plan intake approved)
Routing - PLAN CHECK5/21/2019 5/22/2019 PASS
DetailsCarl Westfall
Back from the Permits Desk. Plan mod review approved
Plan Reviewer's activity  5/22/2019 PASS
2nd plan mod review approved
Permit Ready to Issue  5/22/2019 DONE
Plan Mod Approved
Routing - PLAN CHECK5/17/2019 5/20/2019 PASS
DetailsCarl Westfall
Plan mod plan intake review approved
Plan Modification Accepted  5/17/2019 DONE
plan mod accepted in e plan-changes are parapets, party walls-sheets affected by plan mod are D2.3, A2.3, A3.1 & A4.1-assigned to Carl W
BLD-Framing/Rough-in4/22/20194/22/20194/22/2019PPART
DetailsTony Young
roof framing // Dale Phone #: ###-####,, area by roof units ok,, needs to have 2 layers of 5/8"
CHANGE STATUS TO (ISS)  4/16/2019 DONE
Plan Mod
Telephone call  3/18/2019 DONE
Emailed GC new value to fill out and email back.
OVERRIDE  3/12/2019  
Plan assigned to (CJW)3/4/20193/4/20193/12/2019 PASS
DetailsCarl Westfall
Plan mod - Hyde park shell (plan routed to staff)
Plan Reviewer's activity  3/12/2019 PASS
Plan mod review approved
Permit Ready to Issue  3/12/2019 DONE
MET -
Need revised value-plan mod do not re issue
Routing Off Site - C.D.H3/5/2019 3/11/2019 PASS
DetailsCarl Westfall
Scott Paradis
Routing - MECHANICAL3/5/2019 3/11/2019 PASS
DetailsTroy James
Routing - Design Review3/5/2019 3/8/2019 PASS
DetailsTed Vanegas
Routing - PLUMBING3/5/2019 3/6/2019 PASS
DetailsDaryl Spivey
Install floor sinks so they are visible and accesssible. Shall not be installed under cabinets or equipment.
Routing - PUBLIC WORKS3/5/2019 3/6/2019 PASS
DetailsMorgan Webb
BAKERY AND BAR WILL BE CHARGED UPON TI. OWNER SUPPLIED RESTROOMS AND JAN SINKS
Routing - PLAN CHECK3/5/2019 3/5/2019 PASS
DetailsCarl Westfall
Meeting  3/4/2019 DONE
sent email to rob verifing value "change". informed the value the GC gave is much higher and needed to know if there would be an additional value to that amount
Plan Modification Accepted  3/4/2019 DONE
Structural modifications due to existing conditions discovered in the field. rough in mechanical, plumbing and electrical for southern side future tenant space. modify water meter & service location due to existin conditions discoverd in field
Issue PAID IN FULL permit  2/20/2019 DONE
Inspection Record Card- Bld  2/20/2019 DONE
Meeting  2/19/2019 DONE
emailed bradon (brandon@ekcconstruction.com) informing there are sewer fees that still need to be paid for
OVERRIDE  2/13/2019  
Permit Ready to Issue  2/13/2019 DONE
NEED- all met ( brandon@ekcconstruction.com)
GC FORM
REVISED VALUE
Plan assigned to (CJW)1/7/20191/7/20192/12/2019 PASS
DetailsCarl Westfall
(1st done) 01/24/19 (L3 - 15 days) (ePlan - 31 sheets) Hyde Park - 1509 N. 13th St. Shell & Core ePlan (routed to staff)
Routing Off Site - STRUCTURAL2/6/2019 2/12/2019 PASS
DetailsCarl Westfall
Cory Harelson (KPFF)
PLANS/APPL TAKEN TO FRONT DESK  2/12/2019 DONE
Routing - PLAN CHECK2/5/2019 2/6/2019 PASS
DetailsCarl Westfall
Pending structural - complete and upload plan review report
Routing - Design Review2/6/2019 2/6/2019 PASS
DetailsTed Vanegas
Filled windows and parapet
Plan resubmittals received  2/5/2019 DONE
Route to Impact Fee Review1/31/20192/3/20192/1/2019 PASS
DetailsKarina Myles
Review requested for Commercial Permit
1st review completed  1/31/2019 DONE
Plan resubmittals requested  1/31/2019 DONE
Routing - FIRE1/7/20191/7/20191/30/2019 PASS
DetailsErika Akin
Attached comments to case
Routing PW Solid Waste1/29/2019 1/30/2019 PASS
DetailsEvan Carpenter
Routing - PLAN CHECK1/7/2019 1/28/2019 FAIL
DetailsCarl Westfall
Revised drawings required. Plan review report Emailed to Architect after telephone discussion.
Routing - Erosion and Sediment1/25/2019 1/25/2019 PASS
DetailsAndy J. Long
ESC plan approved. Certified stormwater team designated. Site preparation inspection is required.
Routing Off Site - STRUCTURAL1/7/2019 1/18/2019 FAIL
DetailsCarl Westfall
Cory Harelson (KPFF)
Routing PW Environmental1/7/2019 1/14/2019 PASS
DetailsRick Christenson
Grease Interceptor GW lines shown need on-site inspection
Routing - MECHANICAL1/7/2019 1/10/2019 PASS
DetailsChad Schwendiman
Routing - PUBLIC WORKS1/7/2019 1/8/2019 PASS
DetailsMorgan Webb
Routing - PLUMBING1/7/2019 1/7/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC. See redline remarks.
Routing - Addressing1/7/2019 1/7/2019 PASS
DetailsDoug Chausow
Routing - Design Review1/7/2019 1/7/2019 PASS
DetailsTed Vanegas
Intake Approval  1/4/2019 PASS
DetailsJavier Guzman
Intake Approval  12/31/2018 FAIL
DetailsJoe Bruce
1) Currently enforced codes on sheet A0.1 reflect and old code cycle. Update the currently enforced codes found on our website: https://pds.cityofboise.org/media/1951/currently-adopted-building-codes-12-27-17.pdf
2) License for Robert Thornton has expired as of 12/3/2018. Provide a documentation showing that license has been renewed.
3) Form #310 = Statement of Special Inspections could not be located in the documents folder. Provide this document stamped by the structural engineer.
4) Update the lighting compliance certificate on sheet E3.1. Interior lighting compliance certificate references an older version of ASHRAE. The current version adopted by the 2015 IECC is the 2013 version.
Application received  12/29/2018 DONE
Application submitted via PDS Online on Dec 29 2018 11:52AM