BLD-Final | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for area of work complete, signature card not available for signature.
dALE Phone #: ###-####
|
Zoning Approval | 6/19/2019 | 6/19/2019 | 6/19/2019 | | DONE |
Ted Vanegas
|
|
|
|
FIRE-Final Inspection | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PART |
Jim Page
|
|
|
No fire sprinkler, no fire alarms, fire extinguishers in the 1509 addressed area are placed with current inspection tags. Partial final for life fire safety inspection complete for the 1509 address side of the core and shell project, restrooms on the 1511 address side are part of the core and shell remodel, restrooms on mentioned side will still need to be completed for core and shell sign off for life fire safety. Per conversation with Ron Johnson with Boise Fire a 90 day TCO is authorized contingent on the restrooms being completed on the 1511 address side.
Dale Phone #: ###-####
|
BLD-Framing/Rough-in | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PART |
Tony Young
|
|
|
Dale Phone #: ###-####// 2 hour firewall on north side,, beam/post connections
|
BLD-Final | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | NR |
Tony Young
|
|
|
DALE Phone #: ###-####
|
BLD-Framing/Rough-in | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PART |
Tony Young
|
|
|
DALE Phone #: ###-####,, roof area on north unit ok
|
CHANGE STATUS TO (ISS) | | | 5/28/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 5/22/2019 | | |
|
|
|
|
Plan assigned to (CJW) | 5/17/2019 | 5/17/2019 | 5/22/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - Hyde Park shell and core (plan intake approved)
|
Routing - PLAN CHECK | 5/21/2019 | | 5/22/2019 | | PASS |
Carl Westfall
|
|
|
Back from the Permits Desk. Plan mod review approved
|
Plan Reviewer's activity | | | 5/22/2019 | | PASS |
|
|
|
2nd plan mod review approved
|
Permit Ready to Issue | | | 5/22/2019 | | DONE |
|
|
|
Plan Mod Approved
|
Routing - PLAN CHECK | 5/17/2019 | | 5/20/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod plan intake review approved
|
Plan Modification Accepted | | | 5/17/2019 | | DONE |
|
|
|
plan mod accepted in e plan-changes are parapets, party walls-sheets affected by plan mod are D2.3, A2.3, A3.1 & A4.1-assigned to Carl W
|
BLD-Framing/Rough-in | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | PART |
Tony Young
|
|
|
roof framing // Dale Phone #: ###-####,, area by roof units ok,, needs to have 2 layers of 5/8"
|
CHANGE STATUS TO (ISS) | | | 4/16/2019 | | DONE |
|
|
|
Plan Mod
|
Telephone call | | | 3/18/2019 | | DONE |
|
|
|
Emailed GC new value to fill out and email back.
|
OVERRIDE | | | 3/12/2019 | | |
|
|
|
|
Plan assigned to (CJW) | 3/4/2019 | 3/4/2019 | 3/12/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - Hyde park shell (plan routed to staff)
|
Plan Reviewer's activity | | | 3/12/2019 | | PASS |
|
|
|
Plan mod review approved
|
Permit Ready to Issue | | | 3/12/2019 | | DONE |
|
|
|
MET -
Need revised value-plan mod do not re issue
|
Routing Off Site - C.D.H | 3/5/2019 | | 3/11/2019 | | PASS |
Carl Westfall
|
|
|
Scott Paradis
|
Routing - MECHANICAL | 3/5/2019 | | 3/11/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/5/2019 | | 3/8/2019 | | PASS |
Ted Vanegas
|
|
|
|
Routing - PLUMBING | 3/5/2019 | | 3/6/2019 | | PASS |
Daryl Spivey
|
|
|
Install floor sinks so they are visible and accesssible. Shall not be installed under cabinets or equipment.
|
Routing - PUBLIC WORKS | 3/5/2019 | | 3/6/2019 | | PASS |
Morgan Webb
|
|
|
BAKERY AND BAR WILL BE CHARGED UPON TI. OWNER SUPPLIED RESTROOMS AND JAN SINKS
|
Routing - PLAN CHECK | 3/5/2019 | | 3/5/2019 | | PASS |
Carl Westfall
|
|
|
|
Meeting | | | 3/4/2019 | | DONE |
|
|
|
sent email to rob verifing value "change". informed the value the GC gave is much higher and needed to know if there would be an additional value to that amount
|
Plan Modification Accepted | | | 3/4/2019 | | DONE |
|
|
|
Structural modifications due to existing conditions discovered in the field. rough in mechanical, plumbing and electrical for southern side future tenant space. modify water meter & service location due to existin conditions discoverd in field
|
Issue PAID IN FULL permit | | | 2/20/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/20/2019 | | DONE |
|
|
|
|
Meeting | | | 2/19/2019 | | DONE |
|
|
|
emailed bradon (brandon@ekcconstruction.com) informing there are sewer fees that still need to be paid for
|
OVERRIDE | | | 2/13/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 2/13/2019 | | DONE |
|
|
|
NEED- all met ( brandon@ekcconstruction.com)
GC FORM
REVISED VALUE
|
Plan assigned to (CJW) | 1/7/2019 | 1/7/2019 | 2/12/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 01/24/19 (L3 - 15 days) (ePlan - 31 sheets) Hyde Park - 1509 N. 13th St. Shell & Core ePlan (routed to staff)
|
Routing Off Site - STRUCTURAL | 2/6/2019 | | 2/12/2019 | | PASS |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/5/2019 | | 2/6/2019 | | PASS |
Carl Westfall
|
|
|
Pending structural - complete and upload plan review report
|
Routing - Design Review | 2/6/2019 | | 2/6/2019 | | PASS |
Ted Vanegas
|
|
|
Filled windows and parapet
|
Plan resubmittals received | | | 2/5/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/31/2019 | 2/3/2019 | 2/1/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/31/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/31/2019 | | DONE |
|
|
|
|
Routing - FIRE | 1/7/2019 | 1/7/2019 | 1/30/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Solid Waste | 1/29/2019 | | 1/30/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLAN CHECK | 1/7/2019 | | 1/28/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required. Plan review report Emailed to Architect after telephone discussion.
|
Routing - Erosion and Sediment | 1/25/2019 | | 1/25/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified stormwater team designated. Site preparation inspection is required.
|
Routing Off Site - STRUCTURAL | 1/7/2019 | | 1/18/2019 | | FAIL |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing PW Environmental | 1/7/2019 | | 1/14/2019 | | PASS |
Rick Christenson
|
|
|
Grease Interceptor GW lines shown need on-site inspection
|
Routing - MECHANICAL | 1/7/2019 | | 1/10/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PUBLIC WORKS | 1/7/2019 | | 1/8/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 1/7/2019 | | 1/7/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC. See redline remarks.
|
Routing - Addressing | 1/7/2019 | | 1/7/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Design Review | 1/7/2019 | | 1/7/2019 | | PASS |
Ted Vanegas
|
|
|
|
Intake Approval | | | 1/4/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 12/31/2018 | | FAIL |
Joe Bruce
|
|
|
1) Currently enforced codes on sheet A0.1 reflect and old code cycle. Update the currently enforced codes found on our website: https://pds.cityofboise.org/media/1951/currently-adopted-building-codes-12-27-17.pdf
2) License for Robert Thornton has expired as of 12/3/2018. Provide a documentation showing that license has been renewed.
3) Form #310 = Statement of Special Inspections could not be located in the documents folder. Provide this document stamped by the structural engineer.
4) Update the lighting compliance certificate on sheet E3.1. Interior lighting compliance certificate references an older version of ASHRAE. The current version adopted by the 2015 IECC is the 2013 version.
|
Application received | | | 12/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 29 2018 11:52AM
|