BLD-Final | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | PASS |
Tony Young
|
|
|
Call dan for access Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | DONE |
Tony Young
|
|
|
Call dan for access Phone #: ###-#### Inspection requested via web by Daniel Appel/// 3.52
|
BLD-Wall cover | 5/29/2019 | 5/30/2019 | 5/31/2019 | P | PEND |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, ok pending contractor verifying 6 sided coverage
|
BLD-Energy code compliance | 5/31/2019 | 5/31/2019 | 5/31/2019 | A | PART |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, contractor to verify 6 sided coverage happened on knee walls in attic, self certify
|
BLD-Energy code compliance | 5/29/2019 | 5/30/2019 | 5/30/2019 | P | NR |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 5/24/2019 | 5/24/2019 | 5/24/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 5/20/2019 | 5/22/2019 | 5/22/2019 | P | PART |
Tony Young
|
|
|
Jake Phone #: ###-####,, strap,, brace trusses,, ok to insulate
|
BLD-Wall Bracing | 5/2/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Brandon Shaw
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Foundation | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | PART |
Tony Young
|
|
|
Chris- foundation wall Phone #: ###-####,, work in progress
|
BLD-Footing | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, work in progress
|
Issue PAID IN FULL permit | | | 4/15/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/15/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/15/2019 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 1/2/2019 | 1/2/2019 | 1/11/2019 | | DONE |
Jenny Nelson
|
|
|
01/11 sfd L1 ePlan. 1st complete 1/2, wall bracing panel lengths, spray foam report, waiting for planning
|
Routing - PLAN CHECK | 1/11/2019 | | 1/11/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 1/11/2019 | | DONE |
|
|
|
|
1st review completed | | | 1/4/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 12/31/2018 | | 1/4/2019 | | PASS |
Brent Moore
|
|
|
|
Route to Impact Fee Review | 12/31/2018 | 1/3/2019 | 1/2/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 12/31/2018 | | 1/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Plan assigned to (M_H) | 12/31/2018 | | 1/2/2019 | | DEFR |
Michael Hanson
|
|
|
01/11 #402 L1 ePlan
|
Routing - PLAN CHECK | 12/31/2018 | | 1/2/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 12/31/2018 | | 1/2/2019 | | PASS |
Troy James
|
|
|
|
Application received | | | 12/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 31 2018 10:14AM
|
Plans ACCEPTED BY PLAN TECH | | | 12/31/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/31/2018 | | DONE |
|
|
|
|
Intake Approval | | | 12/31/2018 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 12/31/2018 | | 12/31/2018 | | PASS |
Morgan Webb
|
|
|
|