Second Notice | | 7/20/2019 | 8/5/2019 | | DONE |
|
|
|
mailed on 8-5-2019
|
First Notice | | 6/23/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
Permanent Occupancy | | | 6/13/2019 | | DONE |
|
|
|
|
BLD-Final | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PASS |
Mike Jordan
|
|
|
Santiago Phone #: ###-####. OK for perm occ.
|
Telephone call | | | 6/12/2019 | | DONE |
|
|
|
left message on ###-####, was calling customer back to informed him that he will need ACHD signature and that he will need to speak to the plan reviewer on the Mechanical signature that is required to get occupancy.
|
FIRE-Final Inspection | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Santigao Phone #: ###-####
|
FIRE-Final Inspection | 5/30/2019 | 5/30/2019 | 5/31/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide address per fire review notes #8 and #11, post the occupant load pr drawing A1.0, provide aisle ways as per drawing A1.0, remove the thumbturn dead bolts from the rear exit door and the restroom door, mount the fire extinguisher in a normal path of travel as discussed, provide testing of all exit signs and emergency lights.
Sontiago Phone #: ###-####
|
BLD-Framing/Rough-in | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Mike Jordan
|
|
|
Call for lock box info // Santiago Phone #: ###-####. Interior steel stud framed walls ok and bar ok.
|
BLD-Framing/Rough-in | 3/5/2019 | 3/5/2019 | 3/5/2019 | P | PASS |
Mike Jordan
|
|
|
Call for access // Santiago Phone #: ###-####. Interior steel stud framed wall for office ok.
|
Plan assigned to (JG) | 1/15/2019 | 1/15/2019 | 3/1/2019 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 1/24 L2 Taste Asian Bistro, ePlan
|
Routing - Design Review | 3/1/2019 | | 3/1/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 3/1/2019 | | 3/1/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/1/2019 | | DONE |
|
|
|
Need
Revised Value
(EARLY START BLD19-00448 NEEDS TO BE DOC FINALED WHEN THIS PERMIT IS ISSUED)
|
Issue PAID IN FULL permit | | | 3/1/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/1/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/8/2019 | | 2/13/2019 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 2/13/2019 | | DONE |
|
|
|
|
Routing - FIRE | 2/8/2019 | 2/8/2019 | 2/12/2019 | | PASS |
Mark Scharfen
|
|
|
IFC 2nd Review Complete 2.12.2019.pdf
|
Routing - Design Review | 2/8/2019 | | 2/8/2019 | | FAIL |
Andrea Tuning
|
|
|
Design Review is required.
|
Route to Impact Fee Review | 1/25/2019 | 1/28/2019 | 1/29/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
No change in use and no new square footage added, therefore, no impact fees assessed. SLC
|
Routing - FIRE | 1/15/2019 | 1/15/2019 | 1/25/2019 | | FAIL |
Mark Scharfen
|
|
|
1/25/2019 IFC Fire Code review uploaded and architect emailed.
|
Routing - PLAN CHECK | 1/15/2019 | | 1/25/2019 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 1/25/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 1/16/2019 | | 1/23/2019 | | PASS |
Rick Christenson
|
|
|
Facility has Exterior Grease Interceptor.
|
Routing - PUBLIC WORKS | 1/15/2019 | | 1/17/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLUMBING | 1/15/2019 | | 1/16/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Intake Approval | | | 1/11/2019 | | PASS |
Michael Hanson
|
|
|
|
Intake Approval | | | 1/7/2019 | | FAIL |
Michael Hanson
|
|
|
Provide exit sign and portable fire extinguisher locations.
Provide table and chair layout.
Fire sprinkler and fire alarm on code analysis shows yes and no. Please identify
Revise and resubmit.
|
Application received | | | 1/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 4 2019 4:47PM
|