BLD-Final | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | PASS |
Mike Jordan
|
|
|
Heath Phone #: ###-####
|
DOC - Permit Finaled | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | DONE |
Mike Jordan
|
|
|
4.49
|
BLD-Final | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | FAIL |
Mike Jordan
|
|
|
call to meet there // jason Phone #: ###-####. Provide blower dorr test results and post. Everything else ok.
|
BLD-Energy code compliance | 4/22/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Mike Jordan
|
|
|
We will have all walls insulation completed today. Inspection request to check insulation, so we can proceed to start drywall cover. Phone #: ###-#### Inspection requested via web by Jason Tupper
|
BLD-Framing/Rough-in | 4/18/2019 | 4/19/2019 | 4/19/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Wall Bracing | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PASS |
Jim Sly
|
|
|
Shear Wall bracing Inspection request. Phone #: ###-#### Inspection requested via web by Jason Tupper
|
BLD-Foundation | 3/5/2019 | 3/6/2019 | 3/6/2019 | A | CANC |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
BLD-Foundation | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | PART |
Mike Jordan
|
|
|
Sergio Phone #: ###-####
|
BLD-Footing | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PART |
Mike Jordan
|
|
|
Sergio Phone #: ###-####
|
Issue & PRINT permit | | | 2/14/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2019 | | DONE |
|
|
|
|
Meeting | | | 2/12/2019 | | DONE |
|
|
|
customer knows there are still fees due
|
OVERRIDE | | | 2/6/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 1/24/2019 | 1/24/2019 | 2/6/2019 | | DONE |
Jenny Nelson
|
|
|
02/06 sfd L1 ePlan. 2nd review, bracing lengths. 1st complete 01/29 - wall bracing deficiencies, failed planning.
|
Routing - PLAN CHECK | 2/6/2019 | | 2/6/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 2/6/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/1/2019 | | 2/1/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 1/24/2019 | | 1/30/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 1/24/2019 | | 1/29/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PUBLIC WORKS | 1/24/2019 | | 1/29/2019 | | PASS |
Morgan Webb
|
|
|
|
1st review completed | | | 1/29/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 1/24/2019 | | 1/28/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/24/2019 | 1/27/2019 | 1/25/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 1/24/2019 | | 1/24/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 1/24/2019 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/24/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/24/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/22/2019 | | FAIL |
|
|
|
Need to upload each sheet individually.
MET--Square footage needs to be the same on cover sheet as on application. CAN
Need total height on elevations.
|
Application received | | | 1/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 7 2019 6:39AM
|