BLD-Final | 8/20/2019 | 8/21/2019 | 8/21/2019 | A | PASS |
Jim Storey
|
|
|
Brad Phone #: ###-####
|
DOC - Permit Finaled | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 8/21/2019 | 8/21/2019 | 8/21/2019 | A | DONE |
Jim Storey
|
|
|
Brad Phone #: ###-#### 4.6
|
Plan Reviewer's activity | | | 6/21/2019 | | DONE |
Josh Bogle
|
|
|
added DOC noting as-built fire-wall location
|
BLD-Wall cover | 6/4/2019 | 6/4/2019 | 6/4/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: 2088598694 >> Inspection requested via mobile web by Brad
|
BLD-Framing/Rough-in | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PART |
Jim Storey
|
|
|
Phone #: 2088598694 >> Inspection requested via mobile web by Brad need aproval to relocate fire walls. ok to insulate.
|
BLD-Framing/Rough-in | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | FAIL |
Brandon Shaw
|
|
|
Need Mecg rough-in...
|
BLD-Wall Bracing | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: 2088598694 >> Inspection requested via mobile web by Brad
|
BLD-Footing | 4/8/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Jim Storey
|
|
|
Brad-please call for access Phone #: ###-####
|
BLD-Footing | 4/5/2019 | 4/8/2019 | 4/8/2019 | A | CANC |
Jim Storey
|
|
|
Phone #: 2088598694 >> Inspection requested via mobile web by Brad
|
OVERRIDE | | | 3/26/2019 | | |
|
|
|
|
Telephone call | | | 3/26/2019 | | DONE |
|
|
|
voice message to Brad informing him fees due and needing the ACHD Impact fees due or receipt and if inspection is required.
|
Issue PAID IN FULL permit | | | 3/26/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/26/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 3/7/2019 | | 3/26/2019 | | PASS |
Josh Bogle
|
|
|
3/13 duplex conversion, paper - 1st done
|
Routing - PLAN CHECK | 3/26/2019 | | 3/26/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 3/26/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/26/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 3/26/2019 | | DONE |
|
|
|
Need - met
ACHD
|
Plan resubmittals received | | | 3/25/2019 | | DONE |
|
|
|
Three copies of sheets CVR, A-1.1, A-2.1. one copy of site plan(?) taken to Josh
|
1st review completed | | | 3/13/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/11/2019 | | 3/13/2019 | | FAIL |
Josh Bogle
|
|
|
missing section view of fire wall, foundation plan, floor plan of existing home, tempering, etc.
|
Routing - MECHANICAL | | | 3/11/2019 | | PASS |
|
|
|
|
Routing - PLANNING | 3/11/2019 | | 3/11/2019 | | PASS |
Karla Nelson
|
|
|
Per CAA19-00024 the front driveway will need to be removed and replaced with landscaping. Irrigation is required. Sidewalk was waived but curb and gutter will be extended for the full frontage. All parking is off the alley.
|
Routing - PUBLIC WORKS | 3/7/2019 | | 3/11/2019 | | PASS |
Angela Hardy
|
|
|
|
Route to Impact Fee Review | 3/7/2019 | 3/12/2019 | 3/8/2019 | | PASS |
Karina Myles
|
|
|
|
Route to Impact Fee Review | 3/7/2019 | 3/10/2019 | 3/8/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 3/7/2019 | | 3/8/2019 | | PASS |
Doug Chausow
|
|
|
New address added to duplex: 1406 S Gourley St
|
Plans ACCEPTED BY PLAN TECH | | | 3/7/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/7/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/7/2019 | | PASS |
|
|
|
|
Routing Walk-In (Zoning) | 1/7/2019 | 1/7/2019 | 1/7/2019 | A | FAIL |
Karla Nelson
|
|
|
The project is actually an ADU not just an addition. A variance will be needed to allow the larger size along with an ADU application.
|
Application received | | 1/7/2019 | | | |
|
|
|
|